CLAIMANT’s EXHIBIT C 5<br />
Fri 15/01/15 12:46 p.m.<br />
Wright<br />
Amelia Beinhorn<br />
To<br />
From<br />
info@SantosD.eq<br />
secretariat@wright.me<br />
Re Payment TRF 192-I<br />
Dear Mr Lindbergh,<br />
I refer to your email from earlier today. I have realized that there has been a mix up<br />
in our accounting department with the invoice for the fan blades. Unfortunately,<br />
the price per fan blade has been calculated on the basis of the fixed exchange rate<br />
which we agreed for the clamps in the addendum to the contract of 24 October<br />
2010.<br />
As per our contract negotiations and Section 4 of our Development and Sales<br />
Agreement the contract price is calculated on an actual cost plus profit basis. As<br />
you can see from the attached table the costs per fan blade amount to EQD 19,586.<br />
Multiplied with the current exchange rate, which is identical to that at the time of<br />
production of US$ 1 = EQD 1.79, the purchase price is US$ 10,941.90 per blade.<br />
Consequently, the full purchase price for the 2,000 blades amounts to<br />
US$22,723,800.<br />
I apologize for the mistake and have attached a corrected invoice for the fan blades.<br />
Please effect payment of an additional US$ 2,285,240 to our account. We will<br />
naturally bear all the additional costs which may result from that additional<br />
transfer.<br />
Sincerely,<br />
Amelia Beinhorn<br />
Wright Limited<br />
232 Garrincha Street<br />
Oceanside, Equatoriana<br />
T (0) 214-8803<br />
F (0) 214-8809<br />
© Association for the Organisation and Promotion of the Willem C. Vis International Commercial Arbitration Moot 14<br />
Prof. Dr. Stefan Kröll