HBPCL<br />

(APRIL17-VOL.1)<br />

1


EDITORS CORNER<br />

We are here with the first edition of our monthly report . Throughout the process<br />

of making this report, many individuals from our organization have taken time<br />

out to help me out. I would like to take this opportunity to express my gratitude<br />

and appreciation for the support and assistance you all provided to me. I would<br />

like to give a special thanks to Sh.Perveen Puri Ji,Sh.Sanjeev Mahajan Ji,<br />

Sh.Sanjay Gupta Ji and HBPCL organization as a whole for actively participating<br />

in the feedback and contributions for this report via the mailing lists.<br />

Thanks to Sh.PP Semwal Ji for his help in providing me with a working toolset.<br />

Your advice or suggestions will be much appreciated and welcomed....<br />

ANUVRATA PANDEY<br />

SR.ENGG(CIVIL)<br />

2


CONTENT<br />

‣About JSW Group and JSW Energy Limited<br />

‣About HBPCL<br />

‣Organizational Chart-HBPCL<br />

‣Corporate Social Responsibility<br />

‣Sports and Cultural Activities<br />

‣Safety Activities<br />

3


ABOUT JSW GROUP AND JSW ENERGY<br />

An $11 billion conglomerate, JSW Group is one of India's largest<br />

business conglomerates. It is led by Sajjan Jindal and part of the<br />

US $15 billion O. P. Jindal Group. The group has strong footprints<br />

across various sectors namely, Steel, Energy, Minerals, Port &<br />

Infrastructure & Cement in multiple locations across India, US,<br />

South America and Africa. JSW Steel Ltd, JSW Energy, JSW<br />

Infrastructure, Ispat industries Ltd are subsidiaries of JSW<br />

Group.<br />

Today, JSW Energy has a power generation capacity of 4531<br />

megawatts, JSW Steel has one of the largest single blast furnace<br />

with a capacity of 3.3 MTPA, taking JSW’s overall installed<br />

capacity of 14.3 MTPA, JSW Steel is India’s leading private sector<br />

steel producer. The headquarters for JSW group are located at<br />

JSW Centre, Bandra Kurla Complex, Mumbai<br />

4


JSW Energy Limited (the “Company”), a member of the JSW Group, has inter alia<br />

set up business facilities across different states within India. The Company has its<br />

current domestic operations at different locations such as Vijayanagar in<br />

Karnataka, Ratnagiri in Maharashtra , Barmer in Rajasthan and Hydro Project in<br />

Kinnaur,HP through its Subsidiary, and has plans for new projects coming up in<br />

other locations such as Hydro Project at Kuther in Himachal Pradesh, thermal<br />

power plant in Raigarh, Chhattisgarh, etc.Keeping the above in mind, JSW Energy<br />

is not only committed to creating more smiles at every step of the journey, but it is<br />

in constant pursuit of making life better for communities with its various initiatives<br />

in the fields of improving living conditions, promoting social development,<br />

addressing environmental concerns, addressing social inequalities, promoting art<br />

& culture, sports and Swachh Bharat mission amongst others.<br />

5


HBPCL<br />

(KWHEPS)<br />

The Karcham Wangtoo Hydroelectric Plant is a 1,000 megawatts<br />

(1,600,000 hp) run-of-the-river hydroelectric power station on<br />

the Sutlej River in Kinnaur district of Himachal Pradesh, India. The<br />

dam and power station are located between the villages of Karcham<br />

and Wangtoo where the plant also gains its name. first generator was<br />

commissioned in May 2011, the second in June and the final two in<br />

September.The 98 m (322 ft) tall dam at Karcham<br />

(31°3000.26N 78°1039.54E) diverts a substantial portion of the<br />

Sutlej into a 10.48 m (34.4 ft) diameter and 17.2 km (10.7 mi) long<br />

headrace tunnel to the underground power station downstream at<br />

Wangtoo. At the station, the water powers four 250 MW Francis<br />

turbine-generators before it is sent back into the Sutlej via a 1.2 km<br />

(0.75 mi) long tailrace tunnel. The difference in elevation between the<br />

dam and the power station affords a gross hydraulic head of 298 m<br />

(978 ft). Water not diverted by the dam is sent over the spillway and<br />

down the normal course of the river. The main spillway is along the<br />

crest of the dam and is controlled by six radial gates.<br />

6


BASPA(II)<br />

Baspa (Stage II) Hydro-Electric Power Station of 300 MW generating capacity is located<br />

in the higher reaches of Himalayas and is an environment friendly power station, devoid<br />

of any rehabilitation or resettlement.<br />

The diversion barrage is located in village Kuppa near Sangla at EL 2531m and the<br />

powerhouse is located near village Karcham, just upstream of the Karcham Dam. The<br />

Project is a run-of-the river scheme, utilizing a gross head of 716 m between the<br />

barrages. The powerhouse is estimated to generate 1213 GWh in 90% dependable<br />

year. This project was fully commissioned on 8th June 2003 and has been generating<br />

power ever since.<br />

.<br />

7


ORGANIZATIONAL CHART-HBPCL<br />

Sh.Gyan Bhadra<br />

Sr.VP(HOH)<br />

Sh.Perveen Puri<br />

VP(HTC)<br />

Sh.Sanjeev Mahajan<br />

GM(CIVIL)<br />

Sh.Zia ul Hussain<br />

GM(STORE)<br />

Sh.Sanjeev Kango<br />

AGM(ACCOUNTS)<br />

Sh.Ajay Nath<br />

AGM(ONM)<br />

Sh.Sanjay Gupta<br />

DGM(CIVIL)<br />

Sh.RavinderRana<br />

DGM(Baspa P/H)<br />

Sh.Perveen Katoch<br />

DGM(HR&A)<br />

Sh.V S Brar<br />

DGM(HR&A)<br />

Sh.Ishwarappa<br />

ADD.GM(BILLING)<br />

Sh.H R Thakur<br />

DGM(MECHANICAL)<br />

Sh.S S Pathania<br />

CE(ELECTRICAL)<br />

Sh.P K Jha<br />

CE(ELECTRICAL)<br />

8


9


STALL OF HANDLOOM PRODUCTS AT SHOLTU<br />

• An exhibition was installed at Sholtu on 26.04.2017<br />

• Products of Handloom Centres were kept for sale.<br />

10


WORKSHOP FOR ANGANWADI SEVIKAS<br />

• Conducted monthly Workshops for all Anganwadi Sevikas of DIZ at five places.<br />

• Every month the training is scheduled for Anganwadi sevikas at each Supervisors office.<br />

11


FACILITY OF DRINKING WATER IN GP CHAGAON<br />

• To meet the shortage of water in Gram Panchayat Chagaon, HBPCL is providing drinking water<br />

through a water tanker engaged for it.<br />

• A submersible pump is installed near Adit#3 from where the pipeline is scheduled to be laid to Gram<br />

Panchayat Chagaon so that the shortage of water in this Panchayat may be permanently sort out.<br />

12


INAUGURATION & DEDICATION OF GOVT MIDDLE SCHOOL SHOLTU<br />

• The Renovation work of Govt Middle School Sholtu has been completed.<br />

• The School building was inaugurated by Hon’ble Deputy Speaker HP Vidhan<br />

Sabha, on 26.04.2017, and Dedicated to Gram Panchayat Punang.<br />

13


SWACHH BHARAT ABHIYAAN DRIVE<br />

• SBA drive was conducted at Kuppa on 24.04.2017 by Kuppa Staff.<br />

14


TRAINING FOR TEACHERS & STUDENTS IN GOVT<br />

SCHOOLS OF DIZ<br />

• HBPCL has strengthened 05 Labs of 05 Govt. Schools of DIZ by providing<br />

Models and Back drops<br />

• Provided training to the Teachers & students of these Schools by M/S STEM<br />

Learning.<br />

15


PLANTATION DRIVE CONDUCTED ON 29.04.2017 BY JVM AND CSR<br />

NEAR WANGTOO ( DUMPING NO.34)<br />

16


17


To create positive atmosphere among the employees and workers of HBPCL, every month atleast<br />

one sports/cultural program is organized under UMANG initiative. Accordingily, on 27.04.2017<br />

Basketball tournament was organized .<br />

18


19


SAFETY ACTIVITIES<br />

20


FIRE SAFETY<br />

Fire safety week campaign and disaster awareness<br />

21


22


THANK YOU<br />

for your support<br />

‣ Sh.Perveen Puri Ji<br />

‣ Sh.Sanjeev Mahajan Ji<br />

‣ Sh.Sanjay Gupta Ji<br />

‣ Sh.Sanjay Law Ji<br />

‣ Sh.Kanwar Singh Ji<br />

‣ Sh.Naveen Thakur Ji<br />

‣ Sh.Nitin Gupta Ji<br />

‣ Sh.Suresh Negi Ji<br />

‣ Sh.Rajender Verma Ji<br />

‣ Sh.P P Semwal Ji<br />

23<br />

Feedback is welcomed....<br />

ANUVRATA PANDEY<br />

EDITOR