08.11.2017 Views

GV Newsletter 11-17 web

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

GOVERNMENT<br />

ENHANCING OUR<br />

community<br />

PROJECT UPDATES<br />

LONG ROAD<br />

RECONSTRUCTION<br />

The purpose of the Long Road<br />

Reconstruction Project is to<br />

reconstruct a corridor that was<br />

originally paved in 1972. In addition<br />

to the pavement reconstruction, the<br />

project scope involves upgrading the<br />

storm sewer system, replacing a<br />

Southgate waterline main, pedestrian<br />

safety improvements and<br />

undergrounding the overhead power<br />

lines. The work, which began in April,<br />

will continue into December under<br />

the current closure condition. Long<br />

Road will reopen in December,<br />

however, work will continue through<br />

the winter months into the late Spring<br />

of 2018.<br />

Due to winter weather conditions,<br />

paving and landscaping will be<br />

suspended until the spring of 2018. As<br />

weather permits through the winter,<br />

the contractor will continue with<br />

utility and grading activities during<br />

non-rush hour periods with one way<br />

flagging operations.<br />

When paving and landscaping<br />

resumes, it is anticipated to take two<br />

months to complete. While there may<br />

be short-term weekend closures<br />

necessary to perform the remaining<br />

activities in the spring, no long-term<br />

closures of Long Road are planned.<br />

Several unplanned underground utility<br />

conflicts required modifications to the<br />

alignment of the new water line and<br />

the new storm sewer. Unfortunately,<br />

these modifications have caused delays<br />

to the completion date of the project.<br />

While these type of utility conflicts are<br />

not uncommon to encounter during<br />

construction of a project of this size<br />

and scope, the tight timeline to<br />

complete all of the work and then<br />

perform the final paving before winter<br />

was not accomplished.<br />

The map shows the anticipated status<br />

of the project as of the December road<br />

opening date. For additional project<br />

information, please visit the project<br />

<strong>web</strong>site at longroadconstruction.com<br />

or contact John Wannigman, Project<br />

Manager, at jwannigman@greenwood<br />

village.com or at 303-708-6139.<br />

HOLLY STREET<br />

INTERSECTIONS<br />

Work is complete for the Holly Street<br />

Intersection project with the exception<br />

of the landscape walls along the west<br />

side of the new walk at the Powers and<br />

Prentice intersections. These walls were<br />

added to the project to improve the<br />

transition from the new walk to the<br />

existing grades at the landscape<br />

entrances into the Preserve subdivision<br />

and are anticipated to be done in<br />

November.<br />

The project scope includes<br />

rehabilitating the three degraded<br />

intersections at Powers, Berry and<br />

Prentice that were originally<br />

constructed in 2000. The project<br />

consisted of placing an “unbonded<br />

concrete overlay” on top of the<br />

existing concrete intersections at<br />

Powers and Berry. This innovative<br />

solution required less closure time<br />

while still achieving the high quality<br />

colored and stamped concrete look<br />

desired by the community.<br />

For additional project information,<br />

please contact John Wannigman,<br />

Project Manager, at<br />

jwannigman@greenwoodvillage.com<br />

or at 303-708-6139.<br />

BELLEVIEW AND HOLLY<br />

TURN LANE<br />

The construction work at Belleview<br />

and Holly, which occurred during the<br />

late summer of this year, was for the<br />

installation of a northbound right turn<br />

lane. The purpose of the project is to<br />

help alleviate the delays that<br />

northbound traffic experienced at the<br />

intersection. The roadway work was<br />

completed at the end of August and<br />

crews were able to work around the<br />

school hours to minimize the impacts<br />

on traffic. The landscaping work is<br />

currently being completed. The traffic<br />

signal upgrade will occur in 2018 in<br />

coordination with the Colorado<br />

continued on page 13<br />

PG. 12 <strong>GV</strong> NEWSLETTER | NOVEMBER 20<strong>17</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!