GV Newsletter 11-17 web
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
GOVERNMENT<br />
ENHANCING OUR<br />
community<br />
PROJECT UPDATES<br />
LONG ROAD<br />
RECONSTRUCTION<br />
The purpose of the Long Road<br />
Reconstruction Project is to<br />
reconstruct a corridor that was<br />
originally paved in 1972. In addition<br />
to the pavement reconstruction, the<br />
project scope involves upgrading the<br />
storm sewer system, replacing a<br />
Southgate waterline main, pedestrian<br />
safety improvements and<br />
undergrounding the overhead power<br />
lines. The work, which began in April,<br />
will continue into December under<br />
the current closure condition. Long<br />
Road will reopen in December,<br />
however, work will continue through<br />
the winter months into the late Spring<br />
of 2018.<br />
Due to winter weather conditions,<br />
paving and landscaping will be<br />
suspended until the spring of 2018. As<br />
weather permits through the winter,<br />
the contractor will continue with<br />
utility and grading activities during<br />
non-rush hour periods with one way<br />
flagging operations.<br />
When paving and landscaping<br />
resumes, it is anticipated to take two<br />
months to complete. While there may<br />
be short-term weekend closures<br />
necessary to perform the remaining<br />
activities in the spring, no long-term<br />
closures of Long Road are planned.<br />
Several unplanned underground utility<br />
conflicts required modifications to the<br />
alignment of the new water line and<br />
the new storm sewer. Unfortunately,<br />
these modifications have caused delays<br />
to the completion date of the project.<br />
While these type of utility conflicts are<br />
not uncommon to encounter during<br />
construction of a project of this size<br />
and scope, the tight timeline to<br />
complete all of the work and then<br />
perform the final paving before winter<br />
was not accomplished.<br />
The map shows the anticipated status<br />
of the project as of the December road<br />
opening date. For additional project<br />
information, please visit the project<br />
<strong>web</strong>site at longroadconstruction.com<br />
or contact John Wannigman, Project<br />
Manager, at jwannigman@greenwood<br />
village.com or at 303-708-6139.<br />
HOLLY STREET<br />
INTERSECTIONS<br />
Work is complete for the Holly Street<br />
Intersection project with the exception<br />
of the landscape walls along the west<br />
side of the new walk at the Powers and<br />
Prentice intersections. These walls were<br />
added to the project to improve the<br />
transition from the new walk to the<br />
existing grades at the landscape<br />
entrances into the Preserve subdivision<br />
and are anticipated to be done in<br />
November.<br />
The project scope includes<br />
rehabilitating the three degraded<br />
intersections at Powers, Berry and<br />
Prentice that were originally<br />
constructed in 2000. The project<br />
consisted of placing an “unbonded<br />
concrete overlay” on top of the<br />
existing concrete intersections at<br />
Powers and Berry. This innovative<br />
solution required less closure time<br />
while still achieving the high quality<br />
colored and stamped concrete look<br />
desired by the community.<br />
For additional project information,<br />
please contact John Wannigman,<br />
Project Manager, at<br />
jwannigman@greenwoodvillage.com<br />
or at 303-708-6139.<br />
BELLEVIEW AND HOLLY<br />
TURN LANE<br />
The construction work at Belleview<br />
and Holly, which occurred during the<br />
late summer of this year, was for the<br />
installation of a northbound right turn<br />
lane. The purpose of the project is to<br />
help alleviate the delays that<br />
northbound traffic experienced at the<br />
intersection. The roadway work was<br />
completed at the end of August and<br />
crews were able to work around the<br />
school hours to minimize the impacts<br />
on traffic. The landscaping work is<br />
currently being completed. The traffic<br />
signal upgrade will occur in 2018 in<br />
coordination with the Colorado<br />
continued on page 13<br />
PG. 12 <strong>GV</strong> NEWSLETTER | NOVEMBER 20<strong>17</strong>