2nd Stage Compression Project<br />

A major milestone was achieved in December 2017 with<br />

the successful start-up of 2nd Stage compression at TEG. This<br />

project was delivered by ISG - SFDP and was required to<br />

maintain production as the TEG Field reservoir pressure<br />

declines in the future.<br />

The project scope included:<br />

Revamping both TEG Gas Turbine Compressors with 2 stage<br />

bundles.<br />

Installing inter-stage cooling, a new 2nd stage scrubber, new<br />

anti-surge valves, piping and instrumentation.<br />

The project required four and a half months outage of TEG to<br />

complete major retrofit. TEG Supt Anis Militi and Azeddine<br />

Meddour led the TEG Field Ops in shutting down the TEG site<br />

and preparing CoW practices for SFDP contractor.<br />

Smooth commissioning was started in November 2017<br />

Led by Start-up TL Ahmed Guerimeriane.<br />

As construction was completed a comprehensive PSSR process was initiated by TEG Supts to assure<br />

equipment were installed per design and operation readiness was in place.<br />