VAAL UNIVERSITY OF TECHNOLOGY

ANNUAL REPORT 2018

Provisions

The progress during 2018 on the new building construction

projects are as follows:

• Teacher Education Building at EduCity Campus

The construction progress was delayed due to disruptions and

interference by the community, as well as subsequent legal

issues with the Main Building Contractor. The contract with

the Building Contractor was terminated. Council gave approval

to follow the procurement process to appoint a new Building

Contractor, which is currently in progress.

• Turn-key projects: 300 bed Residences at EduCity Campus

The 300 bed Residence at EduCity Campus was completed in

December 2015 but could not be utilized due to unavailability

of bulk services infrastructure. These services have become

available and connection is in progress. The perimeter fencing

is being constructed, and while the project is not yet completed,

we expect occupation to be effective from January 2019

• Engineering Building Extension – Additional Floor

The construction progress was delayed due to legal problems

of the Main Building Contractor. The contract was terminated.

Council gave approval to start with the procurement process of

appointing a new Building Contractor.

Council has also taken note of the rate of increase in operational

expenses especially personnel costs that is higher than the

increase in revenue over recent years as well as the decline

in debt collection due to the fees protest wave of 2015/2016.

Council is of the view that an urgent intervention is required if

we are to stabilize the system and the Institution.

Council and Management will continuously be committed to

managing the Vaal University of Technology in such a way that

VUT will be able to successfully execute its mandate for the

foreseeable future.

PROFESSOR IL RENSBURG

ADMINISTRATOR

MR NP MASUDUBELE

EXECUTIVE DIRECTOR: FINANCE (ACTING)

• Life and Physical Sciences Building

The construction is in progress; however this was interrupted by

unappointed local contractors. Completion of the building will

be achieved before the end of 2019.

• Acquisition of Student housing

The tender process is in progress and the acquisition is expected

to be finalised before the end of 2019.

• ICT Infrastructure Upgrade

The tender process will be started in 2019 for phase one and this

first phase of the project is planned to be completed before the

end of 2019.

Conclusion

In general, the financial situation of the University needs

to be improved in order to render its services effectively.

Through sound financial management, planning and reporting,

supported by ethical financial practices, the University can

reverse this financial instability and strive to be a financially

stable and sustainable Institution. The University endeavours to

achieve this through constant monitoring of developments in

the sector and the financial position of the University.