TABLE 1-3<br />

Guidance for minimum equipment <strong>and</strong> process reliability for water treatment<br />

Component Recommendation<br />

Source<br />

Surface water<br />

Capacity Meet a one-in-50-year drought with due consideration for multiple year<br />

droughts<br />

Intake structures Where intake tower is used, provide two independent intake cells, each<br />

with three intake ports at different elevations<br />

Pumps Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

Groundwater<br />

Capacity Equal or exceed maximum day dem<strong>and</strong> with largest producing well out<br />

of service<br />

Wells Minimum of two<br />

Treatment<br />

Rapid mix Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

Flocculation Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

Sedimentation Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

Disinfection Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

Power Provide primary transmission lines from two separate sources or<br />

st<strong>and</strong>by generator<br />

Finished water storage<br />

Capacity Equal to the average day dem<strong>and</strong> when fire protection is not provided<br />

Meet domestic dem<strong>and</strong> <strong>and</strong> fire flow dem<strong>and</strong> where fire protection is<br />

provided<br />

Distribution<br />

High service pumps Minimum of two; meet the maximum day dem<strong>and</strong> with one unit out of<br />

service<br />

System pressure Minimum of 140 kPa at ground level at all points in the system<br />

Nominal working pressure should be 410 to 550 kPa <strong>and</strong> not less than<br />

240 kPa<br />

Sources: Foellmi, 2005; GLUMRB, 2003.<br />

THE DESIGN AND CONSTRUCTION PROCESSES 1-13