Challenges<br />
� Site:<br />
� Very restricted site; small peninsula on which plant was placed<br />
� Required considerable reclamation from sea to locate full plant<br />
� Required considerable detailed planning in early stages <strong>of</strong> construction<br />
� Very high silt content in water, divers <strong>of</strong> no use<br />
� Cultural differences/sensitivities: AECL, Chinese, Bechtel, Hitachi<br />
� Experience:<br />
� Young Chinese commissioning staff with first time on CANDU station<br />
� Construction contractors had no previous CANDU construction experience, but had<br />
significant experience <strong>of</strong> nuclear power plant construction<br />
� Work to Canadian quality standards not previously performed in China<br />