Maximization <strong>of</strong> Localization<br />
Challenges<br />
• Civil<br />
– Works had been suspended for some time and exposed to natural conditions<br />
– Very limited structural steel industry. Large sections produced in Romania with welded plates<br />
• Mechanical<br />
– Equipment had been installed for long time<br />
• Electrical<br />
– Unit 1-some electrical equipment installed for some time<br />
• Human Resources<br />
– Extensive turn over <strong>of</strong> staff<br />