2003 Feb 12 Actual: 2002 Dec 31 Days Ahead of Schedule - IAEA
2003 Feb 12 Actual: 2002 Dec 31 Days Ahead of Schedule - IAEA
2003 Feb 12 Actual: 2002 Dec 31 Days Ahead of Schedule - IAEA
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
17<br />
Major Achievements<br />
� Shortest construction <strong>of</strong> any NPP in China from 1 st concrete to In-Service (54 months)<br />
� Shortest duration to construct perimeter wall (14 days)<br />
� Best integrated leak rate <strong>of</strong> all CANDU 6 nuclear power plants<br />
� 70 heavy lifts <strong>of</strong> equipment with the VHL crane<br />
� Steam generator installed in 8 hours<br />
� Fuel channels installed in 64 days<br />
� Excellent performance <strong>of</strong> Chinese contractors with experience (50% less NCRs for Unit 2 in<br />
comparison with Unit 1)<br />