19<br />
Reasons for Success <strong>of</strong> the Project<br />
� Client/Owner was fully 100% behind completion <strong>of</strong> project and gave full support to AECL<br />
and its sub-contractors<br />
� Excellent teamwork between all participants<br />
� AECL had available manpower resources with extensive experience <strong>of</strong> construction<br />
management and engineering expertise on overseas projects<br />
� Use <strong>of</strong> Open Top Method <strong>of</strong> Construction<br />
� Use <strong>of</strong> Modularization<br />