Enclosed, the calculations to the planned activities are presented:<br />

Women Hall:<br />

Material Local Currency Euro<br />

Zinc 612.000 229.2<br />

Cement 566.000 211.9<br />

Stone 450.000 168.5<br />

Woods for roof 540.000 202.2<br />

Bricks 600.000 224.7<br />

Sand 480.000 179.7<br />

Door 280.000 104.8<br />

Windows 770.000 288.2<br />

Cabord 650.000 243.4<br />

Table only one 350.000 131.0<br />

2 Sewing Mach. 845.000 316.4<br />

Contractor 2.300.000 861.4<br />

Total 7.558.000 2.830.7<br />

Secresty Calculation<br />

Material Local Currency Euro<br />

Zinc 255.000 095.5<br />

Cement 256.000 095.8<br />

Stones 300.000 112.0<br />

Woods for roof 240.000 089.9<br />

Bricks 360.000 134.8<br />

Sand 240.000 089.9<br />

Door 280.000 104.8<br />

Windows 440.000 164.8<br />

Cabord 450.000 168.5<br />

Table 350.000 131.0<br />

Contractor 1.600.000 599.0<br />

Total 4.471.000 1.787.2<br />

7 www.prosudan.at