07.03.2013 Views

Download - Enercon

Download - Enercon

Download - Enercon

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Picture: Romuald Banik<br />

showing the assembly steps. “Installing an<br />

E-126 is tricky, mainly because of the size<br />

of the components”, he explains. E.g., the<br />

two generator components – rotor and stator<br />

– have to be hoisted separately because<br />

of their weight, i.e. at least until ENERCON<br />

receives the specially made crane scheduled<br />

to be delivered next year.<br />

Nacelle hoisted in three steps<br />

Pointing to a drawing, Behrends shows how<br />

the rotor is heaved onto the stator at 140 m<br />

above the ground. The rotor weighs 140 t<br />

and with only a few centimetres clearance<br />

in the stator, moving it into place is a feat in<br />

itself. To facilitate inserting the rotor, a specially<br />

designed steel support is mounted on<br />

the stator ring and crane wheels are fixed<br />

to the centre of the rotor to ease it into place.<br />

“The steel support beam and crane<br />

wheels are used to guide the rotor into the<br />

exact position.”<br />

In Georgsfeld the rotor blades and hub are<br />

still being lifted separately due to their<br />

weight. “In future, though, we will be hoisting<br />

the machine house, rotor and generator<br />

in three stages”, explains Beherends. At<br />

the next site, hub and rotor are going to be<br />

lifted together and with the new crane, the<br />

generator will be assembled on the ground<br />

for the first time. The key factor is the crane’s<br />

lifting capacity: In Georgsfeld, a Terex<br />

Demag CC 6800 is being used to heave the<br />

enormous components separately. In Estinnes,<br />

weather permitting, a larger Demag<br />

CC 9800 will hoist the entire rotor hub.<br />

In Estinnes, a municipality near Mons in<br />

Wallonia, ENERCON is in the process of building<br />

an E-126 wind farm for WindVision, a<br />

planner/operator firm in Leuven. Two out of<br />

a total of 11 foundations (29 m diameter)<br />

have already been completed. Sixty metres<br />

above the first foundation a tower installation<br />

team is in the process of joining the<br />

next precast tower segment. At the same time,<br />

a bulldozer and compactor/roller are filling<br />

in the soil around the second foundation.<br />

WindVision is having crane platforms<br />

built at two other sites.<br />

120 tons steel in foundation<br />

“The first WEC components arrive in October<br />

and<br />

then we can<br />

start preassembly”,<br />

reports projectmanager,<br />

Olaf Kunert.<br />

The<br />

E-126 foundations<br />

in<br />

Estinnes are<br />

amongst<br />

the largest<br />

ENERCON<br />

has ever<br />

Two pre-assembled rotor blades in Georgsfeld, in the foreground rotor blade steel segment.<br />

Picture: Romuald Banik<br />

Machine house assembly in Georgsfeld.<br />

PRACTICE WINDBLATT 04 | 2008 13<br />

had built. Each foundation consists of more<br />

than 1400 cubic metres of concrete and<br />

more than 120 tons of steel. “The soil is not<br />

stable enough to support the huge load, so<br />

we have to create reinforcing elements”,<br />

Kunert adds.<br />

A special vibratory probe injects approx.<br />

200 vibro-replacement columns for each<br />

foundation. The vibrator first penetrates the<br />

ground until is reaches load bearing soil,<br />

and then the machine fills the void with gravel<br />

as the probe is progressively raised.<br />

Vibration compacts the columns, building a<br />

soil-column matrix able to support the fourmetre<br />

deep foundation.<br />

The first installation technicians will be arriving<br />

soon from Georgsfeld to start preassembly<br />

in Estinnes. Once the nacelles have<br />

been installed in Aurich, the rest of the crew<br />

will also travel to Belgium where the first<br />

hub is scheduled to be lifted in November.<br />

“Because of the particular nature of installation,<br />

we selected technicians with experience<br />

from former E-112-sites. For the E-126<br />

we’re making sure that there are always<br />

enough of such technicians in the teams”,<br />

says site supervisor Behrends. Having assisted<br />

in all E-112/E-126 projects so far, of<br />

course, Behrends will be there, too.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!