6.3 Buried Installation<br />

Trenching Overview<br />

Trenching Installation Notes<br />

The trench should be dug as straight, level and as rock-free as possible. Avoid tight curves. If there are rapid<br />

grade changes, and you are installing CIC, use back-fill to support the conduit. Taking into account NEC 820<br />

and 830 considerations, dig the trench to correct depth.<br />

Mount the reel so that pay-off is underneath toward the direction of the pull. If using CIC, make sure the conduit<br />

is capped.<br />

Pull enough excess cable to permit easy installation at the attachment point and enough to reach a few feet beyond<br />

the pedestal. When in doubt of the exact length, always play out more than you think you will need.