ASSESSMENT OF RESIDUAL LIFE OF GIRDERS OF BRIDGE No

ASSESSMENT OF RESIDUAL LIFE OF GIRDERS OF BRIDGE No

ASSESSMENT OF RESIDUAL LIFE OF GIRDERS OF BRIDGE No

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

a) The type I girders require replacement of top flange plate, all gussets and<br />

corroded bracings along with provision of centralized bearings and<br />

stiffening plates before use. All girders are require to be painted.<br />

b) The type II girders require replacement of corroded gussets and rivets<br />

and need based replacement of top flange at critical locations and<br />

provision of centralized bearings and stiffening plates before use. All<br />

girders are require to be painted.<br />

3.6 The girders require the following prerequisites before the same can be<br />

released for use elsewhere.<br />

a) There is a water pipe line on bridge <strong>No</strong>. 75 provided on bracing between<br />

girders of UP line and DN line for the inhabitants of the island between<br />

bridges <strong>No</strong>. 73 and 75.<br />

b) There is an H.T. electric line on bridge <strong>No</strong>. 75 provide bracing between<br />

girders of UP line and DN line for the inhabitants of the island between<br />

bridges <strong>No</strong>. 73 and 75.<br />

c) The girders have lived part of the useful life in the period between 1927<br />

and 1993 and the balance fatigue life is to be assessed for the section<br />

where the girders are to be used.<br />