05.08.2013 Views

FERC vs NERC: A grid control showdown over cyber security

FERC vs NERC: A grid control showdown over cyber security

FERC vs NERC: A grid control showdown over cyber security

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

WWW.INTELLIGENTUTILITY.COM /// JULY/AUGUST 2011<br />

18<br />

When Congress passed the Energy Policy Act of 2005, it was<br />

a statute that had actually been negotiated in about 2003. So<br />

the provisions in that statute were dealing with the world as<br />

we knew it in 2003.<br />

There was concern that not enough capital was going<br />

into transmission relative to generation. Also, the concern<br />

was that we needed<br />

enough transmission<br />

to ensure that<br />

these new competitive<br />

generators could<br />

get to market, and we<br />

were seeing “congestion”—or,<br />

in other<br />

words, not enough<br />

transmission.<br />

But by 2006, when<br />

the commission implemented<br />

its order,<br />

we were starting to<br />

get more build-out<br />

of transmission. So<br />

the debate was, “Do<br />

we need incentives<br />

now for building out<br />

transmission?” And<br />

some commissioners<br />

thought, “Yes,” and some commissioners said, “It should be<br />

tailored to different kinds of projects.”<br />

As we’ve seen this incentive program implemented from<br />

2006 till now, the industry has changed even more. The new<br />

public policy issue is transmission for getting to new renewables,<br />

to reach renewables and bring them to market.<br />

INTELLIGENT UTILITY How should the commission consider<br />

changes in cost estimates?<br />

KELLY The question is: When a utility says it’s going to cost<br />

$800 million to do this transmission project, should the<br />

commission use that cost estimate?<br />

If the commission then awards “construction work-inprogress”—allowing<br />

the utility to start rec<strong>over</strong>ing investment<br />

costs while construction proceeds—should the commission<br />

hold the utility to the cost estimate as a cap, as an<br />

alternative way of containing costs?<br />

The argument on the other side is: If that’s the approach<br />

the commission takes, everybody’s going to say, “It’s only<br />

an estimate—you never know how much it’s really going<br />

to cost.” So if that’s the commission’s policy, you’re going to<br />

send a signal that people should highball the cost estimates.<br />

INTELLIGENT UTILITY What other factors should the<br />

commission consider in implementing the law?<br />

REGULATORY INTEL<br />

KELLY We have to ask: What’s the commission’s goal<br />

going to be?<br />

Should the commission look at a project and say, “How<br />

risky is this? How hard is it to get permits? How difficult<br />

is it to build? Should we give incentives to help <strong>over</strong>come<br />

particular barriers and difficulties associated with the<br />

particular project? Or do we look at what the project is going<br />

to accomplish from a public policy perspective?”<br />

In other words, is this—from a public policy perspective—<br />

the kind of project we want to incentivize or maybe even<br />

reward? Say, reaching renewables, or bringing in Canadian<br />

hydro, or building a tie-line to Canada, or a project that has<br />

the potential to interconnect the three <strong>grid</strong>s.<br />

Or a third possible way the commission could approach<br />

this is the way it approaches the building of natural gas<br />

pipelines, which is to say, “It’s all important—the build-out<br />

of pipelines is an infrastructure we want to encourage.” So<br />

the commission could say, “At this stage in the evolution of<br />

our <strong>grid</strong>, we just need more transmission, and we want to<br />

encourage it. So we’re going to give incentives to every<br />

transmission project.”<br />

INTELLIGENT UTILITY How do you view future electricity<br />

transmission—in 2015, or 2020?<br />

KELLY It has to do with, “Where are we headed?” We<br />

usually build transmission because we need more transmission.<br />

But if we don’t<br />

need more generation<br />

or need to move genera- “ The new public policy<br />

tion from one place to<br />

issue is transmission<br />

another, we don’t need<br />

more transmission.<br />

for getting to new<br />

Having said that,<br />

however, there are states<br />

renewables, to reach<br />

that are pursuing renewable<br />

portfolio stan-<br />

renewables and bring<br />

dards: Texas, California,<br />

Colorado, New England<br />

them to market.<br />

to an extent, New York<br />

”<br />

to an extent are pursuing<br />

bringing new generation on line. And we are also seeing<br />

the potential for replacement of existing generation with<br />

new generation. So we will need transmission.<br />

INTELLIGENT UTILITY Is there one point you’d like to<br />

make that we haven’t discussed?<br />

KELLY The one point I’d like to make is that achieving<br />

a consensus on what we are trying to accomplish with<br />

transmission is, first, the key to a good transmission policy<br />

and, second, the most difficult thing to achieve.<br />

Phil Johnson is a freelance writer and speechwriter.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!