New York City Department of Environmental Protection ... - NYC.gov
New York City Department of Environmental Protection ... - NYC.gov
New York City Department of Environmental Protection ... - NYC.gov
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
comments to the engineer on 3/24/11 regarding the concrete check dams. A progress meeting<br />
was held with the project representatives on 3/29/11. DEP performed a site visit on 3/29/11;<br />
there were no deficiencies, there was no discharge and the site was vacant. DEP performed a site<br />
visit on 4/7/11; there were no deficiencies, there was no discharge, the site was occupied. DEP<br />
received a sketch <strong>of</strong> where the walls will be installed from the engineer on 4/12/11. DEP<br />
received a copy <strong>of</strong> the outfall pipe finished grade elevations from the engineer on 4/13/11. DEP<br />
performed a site visit on 4/21/11; there were no deficiencies, there was no discharge, the site was<br />
occupied. DEP received the April 2011 meeting minutes from the engineer on 5/6/11. DEP<br />
performed a site visit on 5/10/11; there were deficiencies, there was no discharge, the site was<br />
occupied. DEP sent and received e-mails to and from the engineer on 5/11/11 regarding the<br />
erosion on the north side <strong>of</strong> Rt. 23. DEP received an e-mail from the engineer on 5/12/11 with a<br />
photo that was sent from the contractor. DEP performed a site visit on 5/17/11; there were no<br />
deficiencies, there was no discharge, the site was vacant. DEP sent an e-mail to the engineer on<br />
5/31/11 with photos that were taken at the 5/19/11 site visit. A meeting was held with the project<br />
engineer and contractor on 6/2/11. Structure elevation and spot elevations were taken. DEP<br />
received an e-mail from the engineer on 6/2/11 regarding the adjustments in elevations <strong>of</strong> the<br />
bio-retention basin. DEP called the project inspector on 6/14/11 regarding the bio-retention<br />
basin drainage. Currently, the basis is supposed to drain out completely within 48 hours. It does<br />
not appear to be functioning properly during the standard site visits. Special attention to the<br />
weather forecasts and the basis's elevation needs to be considered. DEP received a call on<br />
6/16/11 from the project inspector regarding the bio-retention. He's going to the site to pull soil<br />
samples <strong>of</strong> the media and sending <strong>of</strong>f to a lab to check if it meets the spec in the approved plans.<br />
DEP called the project inspector on 6/21/11 regarding the bio-retention basin. The project<br />
inspector stated that he was on site yesterday and did not observe any water coming from the<br />
bio-retention basin's under drain. The engineer and the project inspector have looked into their<br />
records whether the media used was tested and when it was installed. After calling the<br />
contractor, the contractor stated that they used the topsoil on site; it supposedly passed their soil<br />
testing near the high limit for testing. Later this week, the contractor is meeting the project<br />
inspector and they will both will be taking soil samples and getting them tested. DEP sent an email<br />
to the engineer on 6/27/11 requesting the testing results regarding the bio-retention basin.<br />
DEP received the Certificate <strong>of</strong> Functional Completion from the engineer on 6/28/11. DEP sent<br />
an internal e-mail on 6/28/11 stating that the bio-retention basin will not hold up the functional<br />
completion for the WWTP. DEP received an e-mail from the engineer on 6/29/11 with the bioretention<br />
flow splitter. DEP received an e-mail from the engineer on 8/17/11 informing DEP that<br />
the soil tests passed the required specifications however the engineer requested the contractor to<br />
dig soil test pits to check the media’s homogeneousness. The contractor will also adjust the one<br />
concrete weir at that time. DEP performed a site visit on 10/3/11; there were deficiencies, there<br />
was no discharge and the site was occupied. A meeting was held with the project inspector on<br />
10/3/11. DEP performed a site visit on 10/11/11; there were deficiencies, there was no discharge<br />
and the site was occupied. DEP received the meeting minutes for construction startup on laterals<br />
and septic tank installation from the engineer on 10/14/11. DEP performed a site visit on<br />
10/17/11; there were deficiencies, there was no discharge and the site was occupied. DEP<br />
received an e-mail from the engineer on 10/18/11 with the WWTP flood damage repair update.<br />
DEP issued a letter to the engineer on 10/19/11 regarding the 10/17/11 site visit and the bioretention<br />
test holes. DEP received a call on 10/19/11 from the engineer regarding the<br />
Bioretention test holes. DEP called the inspector on 10/26/11 regarding the bio-retention basin.<br />
It appears that a portion <strong>of</strong> the Bio-retention basins under drain has been replaced. DEP called<br />
the inspector to confirm that the under drain will be exposed for inspection prior to the media<br />
24