30.12.2013 Views

Gahir, J.S.

Gahir, J.S.

Gahir, J.S.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

MAX. DSP=130mm<br />

MAX. DD=4.9mm<br />

WLD -15.9DMD<br />

CRESCENT<br />

NW<br />

SW<br />

SE<br />

MAX. DSP<br />

MAX. DD<br />

WLD<br />

Figure 4.<br />

Dewatering regime and cofferdam monitoring points.<br />

procured from Japan and had a2to3month delivery<br />

time. Used PU25 sections of some 10 m length were<br />

purchased locally and taken to an onsite yard at the top<br />

of the Spine where 20 m lengths were assembled. To<br />

determine the sheet pile drivability a trial was undertaken<br />

near the Spine portal close to a borehole location<br />

using PU series. The piles were spliced and driven to<br />

depths of 33 m using vibrohammer ICE815C (1250 kN<br />

max centrifugal force) without difficulty.<br />

The newly purchased SX27 sections were taken to<br />

Hamriya Port, about 35 km east of the project site,<br />

where they were chamfered and welded to form 30 m<br />

lengths. Hyperseal DPS-1000 was applied to the pile<br />

clutch. This material can expand up to 10 times its<br />

original volume in fresh water but its performance offshore<br />

is curtailed due to the salinity of sea water and<br />

it expands to half the figure. The piles were paired to<br />

form 1.2 m wide panels, so that each prepared offshore<br />

panel comprised of 4 sheet piles, before being barged<br />

to site.<br />

5.3 Onshore sheet piling<br />

Sheet pile sections, 20 m long and 0.6 m wide, were<br />

pitched into a guide frame capable of accommodating<br />

16 sheet piles and driven one by one with a 1.5 m stick<br />

up. Longer sheet piles could not be accommodated<br />

due to limitation of the crane boom. Ten metre long<br />

pile sections were hooked through the guide frame and<br />

spliced to the driven piles. Driving recommenced using<br />

vibrohammer ICE815C and progress was slow due to<br />

difficult driving. Some hard nodules present within the<br />

calcarenite and the wear and tear on the used piles were<br />

felt to contribute to difficult driving. Additionally two<br />

splices in the desired pile length did not always provide<br />

a plumb vertical section and this led to an increase in<br />

the frictional force in the pile clutch.<br />

At some locations especially on the Crescent piles<br />

were terminated 5m short of the required design penetration<br />

due to refusal with the driving system. A<br />

reassessment of the seepage inflow into the cofferdam<br />

was undertaken using k of calcarenite 2×10 −5 m/s<br />

which indicated that the anticipated inflow in this<br />

area increased 9 times locally with the nett effect that<br />

the overall infow into the cofferdam after draining<br />

increased from 820 m 3 /hr to 1600 m 3 /hr. To cope with<br />

the additional inflow contingency measures were put<br />

in place and comprised of (a) drive secondary short<br />

length sheet piles in local areas at the top of the tunnel<br />

trench excavation (b) increase the number of wells and<br />

(c) increase pump capacity.<br />

5.4 Offshore sheet piling<br />

Offshore piling was undertaken from 2 barges, each<br />

with a 150T crane, and the prepared panels 30 m long<br />

and 1.2 m wide, were driven through a guide frame<br />

using a double clutch vibrohammer ICE1412 (2300 kN<br />

max centrifugal force). The contractor reported difficult<br />

driving conditions which required greater effort<br />

1300

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!