30.12.2013 Views

Gahir, J.S.

Gahir, J.S.

Gahir, J.S.

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Underground Space – the 4 th Dimension of Metropolises – Barták, Hrdina, Romancov & Zlámal (eds)<br />

© 2007 Taylor & Francis Group, London, ISBN 978-0-415-40807-3<br />

Design and construction of a cofferdam for a sub-sea tunnel on The Palm<br />

Jumeirah, Dubai<br />

J.S. <strong>Gahir</strong><br />

Kellogg Brown & Root, Leatherhead, UK<br />

A. Mochizuki<br />

Taisei Corporation, Tokyo, Japan<br />

N.O. Othman<br />

Parsons PTG, Washington, USA<br />

M.A. Qamzi<br />

Nakheel, Dubai, UAE<br />

ABSTRACT: The paper presents design, construction and performance of a sheet piled cofferdam required to<br />

construct a 1.4 km long sub-sea vehicular tunnel in dry conditions. An overview of the challenges faced whilst<br />

piling and how these were overcome are presented. Measures taken to maintain the cofferdam during tunnel<br />

construction are included.<br />

1 INTRODUCTION<br />

The Palm Jumeirah in Dubai, United Arab Emirates,<br />

involves the reclamation of land to form the shape of<br />

a palm tree comprising of a crescent, 16 Fronds, Spine<br />

and Trunk. Reclamation extends some 5.5 km into the<br />

Arabian Gulf and the artificial island is protected at<br />

the seaward side by a rock armoured semi-closed elliptical<br />

Crescent (Figure 1). The resulting development<br />

increases the Dubai shoreline by 75 km and when completed<br />

will provide for a community of about 100,000<br />

people.<br />

To cross a body of water some 500 m wide a sub-sea<br />

vehicular tunnel connects the Spine to the 11.5 km long<br />

Crescent. The tunnel cross-section comprises 3 cells,<br />

the outer cells carrying 3 lanes of traffic in each direction<br />

while the central cell is reserved for services and<br />

emergency evacuation.<br />

The construction methodology adopted was cut and<br />

cover in dry conditions which required a 2.4 km long<br />

sheet piled cofferdam as temporary works, with the<br />

sheet piles acting as cut off to reduce seepage into the<br />

cofferdam to manageable levels. Offshore and onshore<br />

operations were undertaken to install 30 m long steel<br />

sheet piles into the crest of temporary dykes and into<br />

the recently reclaimed islands where the tunnel portals<br />

are located. The construction sequence was to dredge,<br />

form dykes, install sheet piles and drain the cofferdam.<br />

After draining, the dykes provide construction<br />

Figure 1.<br />

Overall view of The Palm Jumeirah.<br />

access to the Crescent, a significant advantage over<br />

an immersed tube approach. The cofferdam constitutes<br />

some 30% of the total project cost of the tunnel<br />

works.<br />

1297


Figure 2.<br />

Tunnel alignments.<br />

Figure 3.<br />

Typical cross section and ground conditions.<br />

2 PROJECT DESCRIPTION<br />

The total length of the tunnel structure is 1398 m and<br />

comprises of a 241 m long Spine portal approach,<br />

969 m of reinforced concrete box section and 188 m<br />

of Crescent portal approach.<br />

The horizontal and vertical alignments were dictated<br />

by a maximum grade of 6% for a 60 kph design<br />

speed, in compliance with Dubai Municipality Geometric<br />

Design Manual for Dubai Roads (1999), and the<br />

need to ensure that the tunnel was sufficiently deep to<br />

maintain a 125 m wide arc-shaped navigation channel<br />

with a minimum draft of 10 m, above the 1.5 m thick<br />

layer of armour protection on the roof slab. The vertical<br />

alignment and the horizontal alignment, which is a<br />

reverse curve with a central straight section, are shown<br />

in Figure 2.<br />

Mean sea level is +1.0 mDMD (Dubai Municipality<br />

Datum, which is 0.09 m below Admiralty Chart<br />

Datum) with a tidal range of 1.2 m between MHHW<br />

and MLLW. The reclaimed islands are at +3 m and<br />

+4 mDMD at the Spine and Crescent, respectively.<br />

Seabed elevations before The Palm reclamation were<br />

in the range −11 m to −12 mDMD. Pre-construction<br />

surveys indicated that the minimum seabed elevation<br />

along the tunnel alignment and the cofferdam<br />

region was −15 m and −19 mDMD respectively, in<br />

areas where materials had been won for breakwater<br />

construction.<br />

A Design and Build contract was awarded to Taisei<br />

Corporation in 2004 for the construction of the<br />

vehicular tunnel.<br />

3 GEOLOGY AND GROUND CONDITIONS<br />

The local geology in the vicinity of the project site<br />

has been shaped by the current hot arid climate and<br />

by fluctuations in sea level and is described by <strong>Gahir</strong><br />

et al. (2006).<br />

Ground conditions were determined by sinking 13<br />

offshore boreholes to a depth of 30 m into the seabed<br />

and 3 boreholes up to 30 m depth on the onshore<br />

reclamation. The minimum elevation explored is<br />

−45 mDMD. The offshore boreholes were drilled<br />

along the alignment of the dykes and are offset up to<br />

230 m from the tunnel centre line. All boreholes were<br />

grouted after completion.<br />

The boreholes revealed that under a 12 m thick<br />

recent fill a 1 m to 2 m thick band of weak caprock<br />

is present which in turn is underlain by 2 m to 4 m<br />

thick layer of medium dense sand. The sand overlies<br />

an 18 m to 22 m thick sequence of very weak to weak<br />

interbedded calcarenite and sandstone. A conglomerate<br />

layer whose upper horizon is some −35 mDMD is<br />

present across the site (Figure 3). The UCS of rock<br />

encountered is in the range 1 to 3.5 MPa. In isolated<br />

boreholes a thin layer of soft silt was recorded<br />

1298


under the fill, and is suspected to be the original<br />

seabed.<br />

In-situ permeability of the rock units, measured<br />

using standard Lugeon tests and variable head permeability<br />

tests, indicated k values ranging from<br />

4×10 −6 to 5×10 −4 m/sec with lower values at depth.<br />

4 DESIGN CONSIDERATIONS<br />

The cofferdam is required for some 17 months and at<br />

peak periods a workforce of about 1000 was expected<br />

within its confines and thus safety was of paramount<br />

consideration in the design process.<br />

The cofferdam outline was dictated by the following<br />

considerations (a) the dykes have a 12 m wide crest at<br />

−2 mDMD; an elevation adopted after a soil-structure<br />

interaction analysis was undertaken for different pile<br />

sections and various crest elevations, to provide a<br />

balance between the fill available and the structural<br />

performance of the piles (b) the sheet piles were<br />

planned 2 m from the seaward edge so that a 10 m<br />

wide corridor was available for a 2 lane temporary<br />

road inside the cofferdam after draining (c) the tunnel<br />

trench at its deepest is −26 mDMD and the trench<br />

slopes, located in interbedded sandstone and calcarenite,<br />

were planned at 1V:0.5 H (d) a 15 m minimum<br />

clearance was maintained from the top of the trench<br />

excavation to the toe of the dyke thus avoiding surcharging<br />

and undermining the stability of the trench<br />

slope and (e) a dyke slope of 1V:4 H from crest to<br />

−10 mDMD and 1V:7 H thereafter, was adopted from<br />

slope stability considerations based on recent experience<br />

gained in the construction of The Palm. A 2.4 km<br />

long cofferdam outline was thus identified having a<br />

plan area of some 300,000 m 2 and a maximum width<br />

of about 400 m. This outline involved 1550 m of offshore<br />

piles and 850 m of onshore piles. Local filling<br />

adjacent to the recently formed islands was undertaken<br />

to maximize land based operations.<br />

Both marine and land driven sheet piles are up to<br />

30 m long and the top of the piles were planned at<br />

+3.3 mDMD for minimal overtopping under storm<br />

surge and wave conditions, and the toe at −26 mDMD<br />

based on seepage analyses which required 1 m minimum<br />

penetration into the lower less permeable sandstone<br />

which underlies the calcarenite. Bending stresses<br />

and deflections complying with Technical Standard<br />

and Commentary for Port and Harbour Facilities<br />

(2001) indicated that pile sections SX27 (section modulus,<br />

z = 2700 cm 3 /m) for the offshore piles, and PU25<br />

(z = 2500 cm 3 /m) for onshore piles were appropriate.<br />

The estimated maximum deflections at the top<br />

of the marine piles, after draining, was calculated to<br />

be about 200 mm and the relative deflection between<br />

+3 m and −2 mDMD i.e. the cantilevered section, to<br />

be about 150 mm. These estimates are based on a<br />

sea level of +2.45 mDMD, to take account of storm<br />

surge, and a horizontal modulus of subgrade reaction<br />

of 10,000 KN/m 2 /m based on an empirical relationship<br />

to an SPT-N value of 5.<br />

Seepage analysis using 2D FLOW with an average<br />

k value determined for each substrata indicated that<br />

some 820 m 3 /hr could be expected under the cofferdam<br />

once steady state conditions had established.<br />

French drains at the base of the tunnel trench, with<br />

pits and submersible pumps of sufficient capacity, and<br />

lines of well point systems were designed to collect the<br />

inflow (Figure 4). The collected inflow was directed<br />

to two locations, one either side of the tunnel trench,<br />

before being pumped back to the sea over each dyke<br />

with due care taken not to erode the outer slope.<br />

5 CONSTRUCTION METHODOLOGY<br />

5.1 Dyke construction<br />

Cutter suction dredgers were used to excavate the tunnel<br />

trench, one for shallow and one for deep dredging<br />

below −15 mDMD, with operations commencing at<br />

the end of the alignment i.e. at the newly formed<br />

islands and progressing towards the centre where the<br />

trench is deepest.The dredgers lowered the seabed elevation<br />

by some 2 m in a single step until the desired elevation<br />

along the tunnel alignment was achieved within<br />

0.5 m of the invert elevation, with the final grade being<br />

achieved using earthworks equipment in dry conditions.<br />

Seabed elevations were constantly monitored<br />

by surveying equipment on the dredger and from a<br />

survey boat.<br />

The dredged material was sucked into the dredger<br />

holds and placed at the dyke locations using a spread<br />

pontoon positioned by GPS and controlled by anchors<br />

and winches. Both dykes were built up concurrently<br />

and care was required to achieve the 1V:4 H<br />

slope by considerably reducing the volume discharged<br />

through the pipe. Total volume for the two dykes<br />

was 920,000 m 3 of which 660,000 m 3 was obtained<br />

from the tunnel trench excavation and the balance<br />

was obtained from a borrow source nearby, with a<br />

small quantity purchased from a supplier. A larger<br />

volume than had been estimated at the tender stage<br />

was necessary due to the flattening of the dyke slopes<br />

from 1V:4 H to 1V:7 H below −10 mDMD as already<br />

described in Section 4. Bathymetric surveys were carried<br />

out after filling to either confirm that the desired<br />

dyke profile had been achieved or identify local areas<br />

requiring additional fill.<br />

5.2 Sheet pile procurement and preparation<br />

Procurement of the 12,500T of sheet piles was a lead<br />

item due to a shortage on the world market. Some<br />

9500T of new SX27 sections in 15 m lengths were<br />

1299


MAX. DSP=130mm<br />

MAX. DD=4.9mm<br />

WLD -15.9DMD<br />

CRESCENT<br />

NW<br />

SW<br />

SE<br />

MAX. DSP<br />

MAX. DD<br />

WLD<br />

Figure 4.<br />

Dewatering regime and cofferdam monitoring points.<br />

procured from Japan and had a2to3month delivery<br />

time. Used PU25 sections of some 10 m length were<br />

purchased locally and taken to an onsite yard at the top<br />

of the Spine where 20 m lengths were assembled. To<br />

determine the sheet pile drivability a trial was undertaken<br />

near the Spine portal close to a borehole location<br />

using PU series. The piles were spliced and driven to<br />

depths of 33 m using vibrohammer ICE815C (1250 kN<br />

max centrifugal force) without difficulty.<br />

The newly purchased SX27 sections were taken to<br />

Hamriya Port, about 35 km east of the project site,<br />

where they were chamfered and welded to form 30 m<br />

lengths. Hyperseal DPS-1000 was applied to the pile<br />

clutch. This material can expand up to 10 times its<br />

original volume in fresh water but its performance offshore<br />

is curtailed due to the salinity of sea water and<br />

it expands to half the figure. The piles were paired to<br />

form 1.2 m wide panels, so that each prepared offshore<br />

panel comprised of 4 sheet piles, before being barged<br />

to site.<br />

5.3 Onshore sheet piling<br />

Sheet pile sections, 20 m long and 0.6 m wide, were<br />

pitched into a guide frame capable of accommodating<br />

16 sheet piles and driven one by one with a 1.5 m stick<br />

up. Longer sheet piles could not be accommodated<br />

due to limitation of the crane boom. Ten metre long<br />

pile sections were hooked through the guide frame and<br />

spliced to the driven piles. Driving recommenced using<br />

vibrohammer ICE815C and progress was slow due to<br />

difficult driving. Some hard nodules present within the<br />

calcarenite and the wear and tear on the used piles were<br />

felt to contribute to difficult driving. Additionally two<br />

splices in the desired pile length did not always provide<br />

a plumb vertical section and this led to an increase in<br />

the frictional force in the pile clutch.<br />

At some locations especially on the Crescent piles<br />

were terminated 5m short of the required design penetration<br />

due to refusal with the driving system. A<br />

reassessment of the seepage inflow into the cofferdam<br />

was undertaken using k of calcarenite 2×10 −5 m/s<br />

which indicated that the anticipated inflow in this<br />

area increased 9 times locally with the nett effect that<br />

the overall infow into the cofferdam after draining<br />

increased from 820 m 3 /hr to 1600 m 3 /hr. To cope with<br />

the additional inflow contingency measures were put<br />

in place and comprised of (a) drive secondary short<br />

length sheet piles in local areas at the top of the tunnel<br />

trench excavation (b) increase the number of wells and<br />

(c) increase pump capacity.<br />

5.4 Offshore sheet piling<br />

Offshore piling was undertaken from 2 barges, each<br />

with a 150T crane, and the prepared panels 30 m long<br />

and 1.2 m wide, were driven through a guide frame<br />

using a double clutch vibrohammer ICE1412 (2300 kN<br />

max centrifugal force). The contractor reported difficult<br />

driving conditions which required greater effort<br />

1300


in getting the necessary penetration than had been<br />

anticipated initially. On average 2 to 3 panels were<br />

being achieved in a 12 hour shift. When the second<br />

barge, operating a week later on the opposite dyke,<br />

also experienced similar difficulties it was recognized<br />

that the problem was not local.<br />

Piling records indicated that the penetration rate<br />

decreased significantly below −17 mDMD in the second<br />

calcarenite layer. A review of the unconfined<br />

compressive strength results indicated weak rock and<br />

that although the presence of hard nodules may explain<br />

some of the driving difficulties, something fundamental<br />

had been overlooked. Pairing the piles doubled the<br />

area at the cutting edge and also doubled the friction<br />

from the fill and underlying rock, and this resistance<br />

could not be overcome by simply doubling the hammer<br />

capacity required for a single pile section.The decision<br />

to pair the piles was taken after discussion with a local<br />

piling contractor who had successfully driven paired<br />

piles but not to the depth required for this project. An<br />

offshore pile driving trial may have revealed the problem<br />

earlier, and more work in this area would have<br />

been useful.<br />

To overcome the difficulties in the short term predriving<br />

was undertaken with a panel connected to a<br />

water jetting system to −25 mDMD and withdrawn,<br />

and the final 1 m was driven with the permanent pile.<br />

Following the initial success with water jetting, a decision<br />

was taken to weld four 25 mm diameter steel pipes<br />

in the corners of all the sheet piles along its total<br />

length and connected to 2 mm diameter jetting nozzles<br />

located near the toe of the sheet pile. The pipes were<br />

hooked to a high pressure pump capable of delivering<br />

250 l/min at 40 bar pressure. Simultaneous water jetting<br />

and driving with the same hammer overcame the<br />

driving difficulties. To make up for lost time a third<br />

barge was mobilized and a night shift introduced. In<br />

86 working days 1290 paired sheet piles were successfully<br />

driven to the desired toe elevation. Towards the<br />

end a production rate of 5 to 6 pairs was being achieved<br />

in a single shift.<br />

5.5 Cofferdam closure<br />

Seven onshore and 2 offshore closures were necessary<br />

to complete the perimeter. Sheet pile sections driven<br />

from the opposite ends were overlapped so that an open<br />

box was formed. A uPVC tube was inserted from the<br />

top of the piles to key into the top of the dyke and<br />

grouted, thus sealing the open box. After setting, a<br />

borehole was drilled through the grout, the dyke and<br />

into seabed extending to the same elevation as the toe<br />

of the sheet piles. A rapid setting chemical grout, colloidal<br />

silica with sodium chloride, was then injected<br />

at 0.5 m centres working from the bottom up. The colloidal<br />

silica when set has a very low permeability, thus<br />

effectively sealing the closure point.<br />

The offshore closure was undertaken during a Neap<br />

tide within a 4 hour window. Due to an increased flow<br />

velocity some scouring of the dyke, up to 2 m deep over<br />

an 8 m long section, was observed by divers deployed<br />

periodically during the course of the works. The dyke<br />

was repaired after closure.<br />

5.6 Draining<br />

Some 4,350,000 m 3 of water inside the cofferdam<br />

(excluding seepage) was pumped out in stages to<br />

reduce the water level from +1mto−23 mDMD. This<br />

was undertaken using 9 high capacity pumps each fitted<br />

with a flow meter, of which 7 were operational at<br />

one time, connected via valves and manifolds to the<br />

discharge pipes and over the northern cofferdam wall<br />

and to sea. The pumps were located on two floating<br />

pontoons placed centrally at the deepest section of the<br />

trench excavation. Discharge was completed in 45 days<br />

and the rate of water level drop was maintained at less<br />

than 1 m/day. Some leaks in the sheet piles joints were<br />

sealed using underwater welding and sealants.<br />

6 IN-SERVICE PERFORMANCE AND<br />

MONITORING<br />

6.1 Summary of instrumentation installed<br />

To provide information on sheet pile deflections, the<br />

deformation of the dykes, and water levels in the cofferdam<br />

6 total station targets with a mirror attachment,<br />

8 inclinometers, 16 observation wells with ground<br />

water loggers, and settlement monitoring stations were<br />

installed at strategic locations and depths. Base readings<br />

were established on top of the sheet piles before<br />

draining and the instruments were installed shortly<br />

thereafter. Temporary bench marks were installed at<br />

50 m intervals on the shoulder of the dyke for monitoring<br />

settlements. Trigger and action values were<br />

identified for each item along with an action plan<br />

should the values be exceeded, and to provide an early<br />

warning system in the event that unanticipated conditions<br />

arise.Typical results are included on Figure 4 and<br />

an aerial view of the cofferdam is shown on Figure 5.<br />

6.2 Strengthening works<br />

A maximum total deflection of some 1000 mm and<br />

a relative deflection of 285 mm was recorded along<br />

a 200 m long section at the end of draining, which<br />

were in excess of the action values set. The measured<br />

deflections, which incorporates pile rotation, is<br />

in an area where the original dredged channel was<br />

the deepest and the dyke height maximum. CPT testing<br />

indicated the presence of very loose material with<br />

entrapped silty clay for which a horizontal modulus<br />

of subgrade reaction of 2000 KN/m 2 /m was appropriate.<br />

A best fit analysis using a 2D FEM analysis with<br />

1301


ITEM<br />

DESIGN / PROCUREMENT<br />

COFFERDAM CONSTRUCTION<br />

TUNNEL CONSTRUCTION<br />

COFFERDAM REMOVAL<br />

TRAFFIC OPERATION<br />

2004 2005 2006<br />

2007<br />

Figure 6.<br />

Overall schedule.<br />

8 HEALTH, SAFETY AND ENVIRONMENT<br />

Figure 5. Aerial view, December 2005.<br />

the surveyed dyke geometry and the lower modulus<br />

value was undertaken to simulate the actual condition,<br />

and indicated that the stresses in the steel piles were<br />

within tolerances. As a result, the trigger values for<br />

sheet pile deflection were revised up to 1250 mm at<br />

the top of the sheet pile as an absolute deflection and<br />

335 mm between +3.0 m and −2.0 mDMD as relative<br />

deflection to reflect yield stress situation. Vibrotreatment<br />

works on 2.5 m grid spacing and to a depth of<br />

15 m were undertaken in this portion of the dyke fill<br />

to densify the material and the crest level was raised<br />

by 2 m to 0 mDMD and the dyke widened locally to<br />

limit further deflections.<br />

6.3 Maintenance<br />

In addition to visual inspections the instruments are<br />

monitored daily. Once steady state conditions had<br />

established there was no further deformation of the<br />

dyke or additional deflections of the sheet piles, other<br />

than minor cyclic fluctuations due to tidal variations.<br />

The measured discharge averages 1650 m 3 /hr and<br />

compares very favourably with the calculated inflow<br />

estimate of 1600 m 3 /hr indicated by the seepage<br />

analysis.<br />

Corrosion of the sheet piles due to seawater<br />

aggressivity was observed along the perimeter. Ultrasonic<br />

testing revealed that the rate of corrosion was<br />

0.8 mm/yr at the upper half, where tidal fluctuations<br />

occur, and 0.3 mm/yr at the lower end of the cantilever<br />

section. A couple of moist areas were observed on the<br />

dyke slope and standpipes were installed in these areas<br />

which recorded water level at a depth of 3.5 m below<br />

the dike slope. The moist spots are related to the capillary<br />

rise in the area and the capillary fringe is consistent<br />

with the results reported by Fookes et al. (1983) for<br />

sandy silts.<br />

7 PROGRAMME<br />

The overall project schedule is shown on Figure 6.<br />

A plan was prepared to evacuate the cofferdam in<br />

an emergency and drills undertaken at periodic intervals<br />

demonstrated that the work force could be safely<br />

evacuated in 8 minutes. Discharge water quality was<br />

visually monitored on a daily basis with water quality<br />

samples analysed weekly.<br />

Whilst draining the cofferdam local fishermen were<br />

engaged to catch fish trapped within its confines using<br />

wire net traps of different sizes, up to 2 m in diameter.<br />

The trapped fish were removed and placed in<br />

oxygenated cool boxes before being returned to sea.<br />

Almost 1900 fish comprising 35 species were safely<br />

returned to open waters.<br />

9 CONCLUSION<br />

The successful completion and draining of the cofferdam<br />

has resulted in a safe environment enabling cut<br />

and cover tunnel construction to proceed. At the time<br />

of writing in September 2006, 85% of the tunnel structure<br />

is complete and the tunnel will be operational in<br />

December. Difficulties encountered whilst pile driving<br />

were successfully overcome with additional effort and<br />

within programme constraints, without compromising<br />

safety.<br />

ACKNOWLEDGEMENTS<br />

The authors are grateful to Nakheel for their kind<br />

permission to publish this paper.<br />

REFERENCES<br />

Dubai Municipality Geometric Design Manual for Dubai<br />

Roads. 1999 Edition.<br />

<strong>Gahir</strong> J.S., Radwanski R. and Hafez T.A. 2006, “Design and<br />

Construction Challenges of Sub-sea Directional Drilled<br />

Crossings on the Palm Jumeriah, Dubai. ITA congress,<br />

Korea.<br />

Technical Standard and Commentaries for Port and Harbour<br />

Facilities in Japan (The Overseas Coastal Area<br />

Development Institute of Japan). 2001 edition.<br />

Fookes P.G., French W. J. and Rice M. M. 1983. The influence<br />

of ground and groundwater geochemistry on construction<br />

in the Middle East. Quarterly Journal of Engineering<br />

Geology, London, 18, 101–128.<br />

1302

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!