GETCO<br />

SCOPE OF WORK:<br />

The scope of work shall be as follows:<br />

(1) The contractor has to make his own arrangement of water for construction activity at his<br />

own cost. However, if possible, on completion of bore well / open well only, the water<br />

supply line from GETCO will be given at one mutually agreed point. Further distribution will<br />

have to be carried out by the contractor as per their requirements at their cost on<br />

chargeable basis at the rates prevailing in GETCO during that period of consumption<br />

prevailing rate is Rs. 2/- per 1000 liter, if metered, otherwise recovery for water charges<br />

will be effected at two percent of the cost of items as executed in which the water supplied<br />

by GETCO, is used, as certified by the EIC.<br />

(2) All the royalties, taxes, government duties or any unforeseen expenses, if required to be<br />

made; shall be borne by the agency. The rates quoted shall be<br />

deemed to account all such factors after careful consideration of work and site condition.<br />

<strong>No</strong> extra claim shall be entertained in any circumstances on any account.<br />

(3) Earth work in filling and spreading in uniform layer of 150 mm thickness of selected yellow<br />

earth with necessary compaction dressing and watering as directed.<br />

(4) Any activity not specifically mentioned in the tender but necessary in the opinion of<br />

engineer in charge of work must be carried out for successful completion of the job.<br />

(5) Payment shall be made in respective items of the work order.<br />

(6) Before taking up construction activity; the agency has to cut the trees which obstruct the<br />

working, of any diameter, bushes, vegetations, i.e. roots, plant, shrubs, grass etc including<br />

stacking and crediting to GETCO as directed with no extra cost.<br />