distributing the water at his own cost. He has to make necessary arrangements,<br />
to avoid any accidents or damage caused due to construction and subsequent<br />
maintenance of the well. He has to obtain necessary approvals from the local<br />
authorities, if required, at his own cost. He shall restore the ground to its original<br />
condition after wells are dismantled on completion of the work or hand over the<br />
well to the UBI without any compensation as directed by the<br />
Architect/Consultant.<br />
39.0 Power Supply:<br />
The Bank shall provide Electricity at one fixed point free of cost but subject to<br />
availability. If Bank is not able to provide Electricity for what so ever the reason/s,<br />
the contractor shall make his own arrangement for power and supply/ distribution<br />
system for driving plant or machinery for the work and for lighting purpose at his<br />
own cost. The cost of running and maintenance of the plants are to included in<br />
his tender prices. He shall pay all fees and charges required for the power supply<br />
and include the same in his tendered rates and hold the owner free from all such<br />
costs. He has to obtain necessary approvals from the appropriate authorities, if<br />
required.<br />
40.0 Treasure trove etc. :<br />
Any treasure trove, coin or object antique which may be found on the site shall<br />
be the property of the UBI and shall be handed over to the bank immediately.<br />
41.0 Method of measurements:<br />
Unless otherwise mentioned in the schedule of quantities or in mode of<br />
measurement or elsewhere in these documents the measurement will be on the<br />
net quantities or work produced in accordance with up to date as per rules laid<br />
down by the Bureau of Indian Standards. In the event any dispute/disagreement<br />
the decision of the Architect/Consultant shall be final and binding on the<br />
contractor.<br />
42.0 Maintenance of registers:<br />
The contractor shall maintain the registers as directed/instructed by the<br />
Bank/Architects as per the approved Performa at site of work and should<br />
produce the same for inspection of the UBI/ the Architect/Consultant whenever<br />
desired by them. The contractor shall also maintain the records/ registers as<br />
required by the local authorities/ Govt. from time to time.<br />
43.0 Force Majeure:<br />
43.1 Neither contractor nor UBI shall be considered in default in performance of their<br />
obligations if such performance is prevented or delayed by events such as but not<br />
to war, hostilities revolution, riots, civil commotion, strikes, lockout, conflagrations,<br />
epidemics, accidents, fire, storm, floods, droughts, earthquakes or ordinances or<br />
any act of god or for any other cause beyond the reasonable control of the party<br />
affected or prevented or delayed. However a notice is required to be given within<br />
Tender Document UBI Deva branch