Project Safety Challenges - Hebron Project
Project Safety Challenges - Hebron Project
Project Safety Challenges - Hebron Project
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Hibernia Southern Extension<br />
<strong>Project</strong> <strong>Safety</strong> <strong>Challenges</strong><br />
Glenn Addison<br />
<strong>Project</strong> Manager<br />
June 29, 2011
Partner Selection – Key to <strong>Safety</strong> Success<br />
HSE Contractors:<br />
– GBS Topsides<br />
– Subsea Equipment Supply<br />
– Dredging of Excavated Drill Centre<br />
– Pipeline, Umbilical, & Subsea Installation<br />
– Platform Drilling<br />
MODU Drilling Contractor – Subsea Drilling<br />
2
All projects have their unique set of SSHE challenges….<br />
• High intensity offshore campaign work<br />
- Short term<br />
- Potential for high consequence events<br />
- New vessels & crews<br />
• Existing safety culture<br />
Congested Deck Space<br />
• Offshore weather – limited windows<br />
Deep Pioneer Technip Vessel<br />
3
All projects have their unique set of SSHE challenges….<br />
• Brownfield Work on Hibernia Platform<br />
- Existing operating facility<br />
- Competing priorities<br />
- High level of activity<br />
- Maintaining a single consistent<br />
safety approach for the platform<br />
- Simultaneous operations<br />
- POB limit<br />
• 2011 Early Dive Program<br />
- Limited to GBS J-tube preparation<br />
- Remainder of project designed for<br />
diverless installation<br />
- Shared program with offshore loading<br />
system replacement<br />
- Tanker loading simultaneous operations<br />
Hibernia Platform<br />
J-tube Bridge Structure & Bell Mouth<br />
4
All projects have their unique set of SSHE challenges….<br />
• NL onshore activities<br />
- Selection of fabrication, shore base,<br />
& supply subcontractors<br />
- Working with HSE contractors to support<br />
improved subcontractor safety performance<br />
- Consistent approach for all ExxonMobil work<br />
in NL<br />
• Drilling<br />
- Maintaining & continuing to improve platform<br />
performance<br />
- Selection of MODU contractor with shared<br />
safety vision<br />
- Engagement with MODU contractor prior to<br />
mob. to meet safety expectations from day one<br />
Fabrication Yard<br />
MODU Rig<br />
5
Successful <strong>Safety</strong> Partnerships Key to Success<br />
The Team and Partner of Choice for Flawless Execution of a Legacy <strong>Project</strong><br />
High Performance Team<br />
Partner of Choice<br />
Flawless Execution<br />
• One Team with Common Goals<br />
• Belief in Nobody Gets Hurt<br />
• Respectful, Caring, & Helpful<br />
• Everyone is a Leader<br />
• Recognition of Success<br />
• Contractors Essential to Success • Nobody Gets Hurt<br />
• Foundation of Trust Mutual Respect • No Spills<br />
• Understanding Needs & Goals<br />
+ = • Minimize Environmental Impacts<br />
• Transparent Honest Communication<br />
• Relationships at Multiple Levels<br />
• Meeting Commitments<br />
Nobody Gets Hurt<br />
6