Examine existing prefeasibility and feasibility studies and other data when<br />
available (The documentation available at CERE’s Library or data room is<br />
provided in Annex 1). Review the investments as previously proposed and revise<br />
the proposed configuration to reflect one that would be competitive, given the<br />
current electricity market and tariff structures.<br />
Conduct preliminary site investigations including hydrological, topographical,<br />
geological and geotechnical studies.<br />
Develop preliminary layouts <strong>of</strong> hydraulic structures, electro-mechanical and<br />
electrical equipment and do selection <strong>of</strong> the main project characteristics such as<br />
installed capacity, energy production, capacity fac<strong>tor</strong>, etc.<br />
Develop preliminary cost estimates based on major quantities and cost items.<br />
Identify potential socio and environmental impacts, and proposed solutions.<br />
Carry out/update the project economic and financial analysis at pre-feasibility<br />
level.<br />
Highlight the main risks facing the project, and possible mitigation measures.<br />
This information will be included in the Consultant’s pre-feasibility report for each<br />
site to be reviewed by PCJ, MEM and the World Bank.<br />
3.4 PHASE II: SCOPE OF THE CONSULTING ASSIGNMENT<br />
Following PCJ’s instruction to proceed with the feasibility study, the Consultant shall<br />
carry out the following Phase II activities:<br />
Continue site investigation works on the sites including major geotechnical<br />
investigations.<br />
Define all key structures and equipment in sufficient detail to obtain quantities for<br />
all items contributing more than about 10% <strong>of</strong> the cost <strong>of</strong> structures and<br />
equipment.<br />
Provide a detailed initial cost estimate for: (i) the initial capital costs including<br />
access roads, transmission interconnection(s) to the grid; (ii) the implementation<br />
<strong>of</strong> the environmental and social management plans; and for (iii) the operations<br />