Provide the base case estimate <strong>of</strong> the annual project output (firm and average<br />
capacity and energy) over the project life/duration <strong>of</strong> the Power Purchase<br />
Agreement (PPA) , and higher and lower bounds.<br />
Estimate the reduction <strong>of</strong> greenhouse gas reduction estimate throughout the life <strong>of</strong><br />
the project<br />
Carry-out an-environmental and social impact assessment and a mitigation plans in<br />
compliance with the ESEE Project Environmental Management Framework and the<br />
Involuntary Resettlement Policy Framework, survey community interest groups<br />
regarding their use <strong>of</strong> water use practices.<br />
Carry out a project economic analysis (Jamaica’s perspective) and a financial<br />
analysis (project owners’ perspective) including capital, operating and<br />
maintenance costs and revenue streams required for cost recovery and return, and<br />
financing plans. The analysis shall consider private sec<strong>tor</strong> arrangements for the<br />
construction and/or operation <strong>of</strong> the hydropower scheme through concessions under<br />
Design, Build, Operate and Own (DBOO). The Consultant shall recommend a<br />
capital structure required to finance and implement the new hydro facility. Local<br />
and overseas partnerships shall be considered.<br />
Determine the best organizational and institutional arrangements for hydropower<br />
management and ownership over the concession period.<br />
.Provide knowledge transfer to PCJ and MEM Staff and tertiary students from the<br />
University <strong>of</strong> the West Indies and the University <strong>of</strong> Technology as it relates to basic<br />
small hydro power design, environmental considerations and basic financial<br />
analyses.<br />
3.5 PHASE I KEY ACTIVITIES<br />
The following paragraphs highlight key activities and products expected from the<br />
Consultant. It is however the responsibility <strong>of</strong> the consultant to define and carry out all<br />
activities necessary to ensure quality and timely delivery <strong>of</strong> the studies.<br />
<br />
Task 1 - A hydrological report shall be prepared based on previous hydrological<br />
analyses and additional data relevant to the site shall be collected from the<br />
relevant government agencies. His<strong>tor</strong>ical flow data obtained from previous studies<br />