UPDATE ON PROJECTS FUNDED<br />

WITH ACOE FY10 FUNDS<br />

• As of 5 Apr 11, the project to expand the existing children’s spray park in the Corkan Recreation<br />

Area at <strong>Fort</strong> <strong>Stewart</strong> was 100% completed.<br />

• Additional paved running/walking trails at Hunter Army Airfield. Phase I – As of 7 Jan 11, work was<br />

100% complete; Phase II – Work is 73% complete. Estimated Completion Date (ECD) is end of April<br />

2011.<br />

• Large electronic media billboards at both <strong>Fort</strong> <strong>Stewart</strong> and Hunter AAF for better community<br />

information. As of 29 Mar 11 work was 100% completed for <strong>Fort</strong> <strong>Stewart</strong> and 7 Apr 11 100%<br />

completed at Hunter AAF.<br />

• A dog exercise park project is 45% complete and ECD is end of Jun 11. This park is located at<br />

<strong>Fort</strong> <strong>Stewart</strong> near Holbrook pond where dogs can run leash free.<br />

• Boat ramps at Halstrom Lake at Hunter AAF were 100% completed as of Nov 2010.<br />

• The <strong>Fort</strong> <strong>Stewart</strong> Holbrook pond boat ramp project is pending allocation of funds for completion.<br />