Design & Construction - Charlotte's East/West Systems Interconnects<br />
Prior<br />
Funding<br />
Cumulative<br />
Transfer or<br />
Lapsed Funding<br />
FY2012<br />
Funding<br />
FY2013<br />
Funding<br />
Future<br />
Funding<br />
Total<br />
Funding<br />
<strong>District</strong> Budgeted - Ad Valorem<br />
Based Revenue<br />
010 General Fund (<strong>District</strong>wide) 454,447 0 126,489 82,319<br />
0 663,255<br />
020 Peace River Basin 452,982 0 2,268 82,275<br />
0 537,525<br />
120 General Fund - Peace River 0 0 125,000 0<br />
0 125,000<br />
Project Funds Not Budgeted by the<br />
<strong>District</strong><br />
Charlotte County 900,000 0 250,000 164,550<br />
0 1,314,550<br />
Total<br />
$2,640,330<br />
Critical Project Milestones<br />
Projected<br />
Amended<br />
Actual<br />
Commence Design 01/01/2010 01/13/2010<br />
Complete Design Stage 1 05/01/2010 12/30/2011 12/30/2011<br />
Complete Design Stage 2 07/01/2010 06/01/2012<br />
Commence Construction Stage 1 08/01/2010 04/16/2012<br />
Complete Design Stage 3 10/01/2010 03/01/2012<br />
Commence Construction Stage 2 11/01/2010 09/17/2012<br />
Commence Stage 3 Construction 02/01/2011 06/15/2012<br />
Complete Stage 1 Construction 02/01/2011 03/31/2013<br />
Complete Stage 2 Construction 05/01/2011 06/30/2013<br />
Complete Stage 3 Construction 12/31/2012 04/30/2013<br />
Contract Close-out 12/31/2013<br />
Offset Report 01/01/2014<br />
Status As Of March 02, 2012<br />
The cooperative funding agreement was executed on December 8, 2009, and the cooperator was issued notice to proceed. The<br />
County has started design for the 12 inch reclaimed water line in Stage 1 but has experienced delays due to weather and other<br />
work assignments. The County has decided to include a wastewater force main and water line to Stage 1. The design for Stage 1<br />
is now complete. Plans and specifications were approved by the <strong>District</strong> January 6, 2012. The bid package is under development.<br />
The County hired Stantec to design Stage 2 (Pump Facility) and Stage 3 (Storage Pond) on July 21, 2011. Both Stages 2 & 3 are<br />
now under design. A revised project milestone schedule was approved January 13, 2012. To date, $1,150,000 has been<br />
budgeted, of which $0 has been reimbursed.<br />