Morningside Report and Summary Here - KiwiRail
Morningside Report and Summary Here - KiwiRail
Morningside Report and Summary Here - KiwiRail
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
individual crossings would be staggered which would result in a restricted width pathway in<br />
parts. Continuous pour concrete was not considered as a suitable construction method<br />
because of its tendency to crumble with movement from passing trains <strong>and</strong> the longer<br />
installation period required, over 24 hours.<br />
A rubber panel crossing was considered for the <strong>Morningside</strong> level crossing, however, the<br />
time to procure including design (4 months) was too long to meet the construction timeframe.<br />
The crossing at <strong>Morningside</strong> was therefore built to the specifications applicable to the<br />
construction of an asphalt road crossing as per Track <strong>and</strong> Structures Engineering Group<br />
Wellington Asphalt Road Crossing Drawing CE No 100 405.<br />
The project team had selected this st<strong>and</strong>ard because of its use in other existing pedestrian<br />
crossings in Auckl<strong>and</strong>.<br />
Figure 6<br />
<strong>Morningside</strong> Drive pedestrian crossing after completion of upgrading<br />
June 2011<br />
<strong>Report</strong> on Collision Train 126 with Power Wheelchair, <strong>Morningside</strong>, 25 February 2013 Page 11