02.10.2014 Views

Morningside Report and Summary Here - KiwiRail

Morningside Report and Summary Here - KiwiRail

Morningside Report and Summary Here - KiwiRail

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Undertaking the Work<br />

What do the Codes <strong>and</strong> St<strong>and</strong>ards require in terms of undertaking works?<br />

The information from M125/6 Track Inspection report prepared by Track Inspectors which<br />

identifies work required is sighted by the Area Manager, then assessed by the Field<br />

Engineer <strong>and</strong> is then logged into the Asset Data Base (ADB). A summary report (which lists<br />

the work required) is then created from ADB for review by line management (Field Engineer<br />

<strong>and</strong>/or Area Manager) who then schedule the work for the appropriate ganger (being the<br />

person responsible for the team carrying out the work).<br />

Once work is completed, the completed job list is then returned to the Field Engineer who<br />

reviews the list, which is then entered as complete, with the completed date in the relevant<br />

record.<br />

This process is set out in a training document <strong>and</strong> is customary practice but is not codified.<br />

What happened in relation to the works on the Crossing?<br />

The information from the relevant M125/6 Inspection <strong>Report</strong> was entered into the ADB, but<br />

without review by the Field Engineer. When entered into the ADB system, the P4<br />

prioritisation was accorded a six month repair timeframe, not the 90 days as it would have<br />

been in accordance with the initial intention of the Track Inspector or if it had been assessed<br />

as P4 in accordance with CSP22.<br />

A Block of Line was in place during the Christmas 2012 – New Year 2013 period for the<br />

entire Auckl<strong>and</strong> Metropolitan Area for the purposes of continuing major project work in the<br />

absence of trains. The outst<strong>and</strong>ing work listed on the M125/6 Track Inspection <strong>Summary</strong><br />

<strong>Report</strong> dated 21 December 2012 which included the work required at the <strong>Morningside</strong><br />

crossing was to be accommodated within the project-related Block of Line program.<br />

The summary report still showed the work at <strong>Morningside</strong> crossing as a P4 with a 6 month<br />

maximum completion date from initial inspection date of 5 September 2012.<br />

Over the Christmas period the Track Inspector in charge of the maintenance gang (not the<br />

Inspector who had identified the uneven surface) had concentrated his efforts on repairing<br />

EM80 (Track Recording Car) track geometry exceedances recorded on the M125/6 Track<br />

Inspection <strong>Summary</strong> <strong>Report</strong> dated 21 December 2012 <strong>and</strong>, although he had rectified a fault<br />

at the first pedestrian crossing at <strong>Morningside</strong>, he was not equipped or resourced to respond<br />

to the issues raised in the 5 September 2012 M125/6 Inspection <strong>Report</strong> in relation to the<br />

second pedestrian crossing <strong>and</strong> the original 6 months for completion had not yet expired.<br />

The copy of the M125/6 Track Inspection <strong>Summary</strong> <strong>Report</strong> was subsequently endorsed with<br />

the date “29/12/12” signifying that the work had been completed. It was possible that the<br />

Track Inspector had signed off the work on both pedestrian crossings as having been<br />

completed, even though the work had only been completed on one, by mistake. The close<br />

physical proximity of the pedestrian crossings, separated only by the vehicle level crossing,<br />

<strong>and</strong> their proximity on the <strong>Summary</strong> <strong>Report</strong> would tend to support this.<br />

That information was entered into the ADB on 4 January 2013. At that time the TID<br />

reference was transferred as completed from the M125/6 Track Inspection <strong>Summary</strong> <strong>Report</strong><br />

to the ADB Archive (Complete).<br />

<strong>Report</strong> on Collision Train 126 with Power Wheelchair, <strong>Morningside</strong>, 25 February 2013 Page 15

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!