Morningside Report and Summary Here - KiwiRail
Morningside Report and Summary Here - KiwiRail
Morningside Report and Summary Here - KiwiRail
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Undertaking the Work<br />
What do the Codes <strong>and</strong> St<strong>and</strong>ards require in terms of undertaking works?<br />
The information from M125/6 Track Inspection report prepared by Track Inspectors which<br />
identifies work required is sighted by the Area Manager, then assessed by the Field<br />
Engineer <strong>and</strong> is then logged into the Asset Data Base (ADB). A summary report (which lists<br />
the work required) is then created from ADB for review by line management (Field Engineer<br />
<strong>and</strong>/or Area Manager) who then schedule the work for the appropriate ganger (being the<br />
person responsible for the team carrying out the work).<br />
Once work is completed, the completed job list is then returned to the Field Engineer who<br />
reviews the list, which is then entered as complete, with the completed date in the relevant<br />
record.<br />
This process is set out in a training document <strong>and</strong> is customary practice but is not codified.<br />
What happened in relation to the works on the Crossing?<br />
The information from the relevant M125/6 Inspection <strong>Report</strong> was entered into the ADB, but<br />
without review by the Field Engineer. When entered into the ADB system, the P4<br />
prioritisation was accorded a six month repair timeframe, not the 90 days as it would have<br />
been in accordance with the initial intention of the Track Inspector or if it had been assessed<br />
as P4 in accordance with CSP22.<br />
A Block of Line was in place during the Christmas 2012 – New Year 2013 period for the<br />
entire Auckl<strong>and</strong> Metropolitan Area for the purposes of continuing major project work in the<br />
absence of trains. The outst<strong>and</strong>ing work listed on the M125/6 Track Inspection <strong>Summary</strong><br />
<strong>Report</strong> dated 21 December 2012 which included the work required at the <strong>Morningside</strong><br />
crossing was to be accommodated within the project-related Block of Line program.<br />
The summary report still showed the work at <strong>Morningside</strong> crossing as a P4 with a 6 month<br />
maximum completion date from initial inspection date of 5 September 2012.<br />
Over the Christmas period the Track Inspector in charge of the maintenance gang (not the<br />
Inspector who had identified the uneven surface) had concentrated his efforts on repairing<br />
EM80 (Track Recording Car) track geometry exceedances recorded on the M125/6 Track<br />
Inspection <strong>Summary</strong> <strong>Report</strong> dated 21 December 2012 <strong>and</strong>, although he had rectified a fault<br />
at the first pedestrian crossing at <strong>Morningside</strong>, he was not equipped or resourced to respond<br />
to the issues raised in the 5 September 2012 M125/6 Inspection <strong>Report</strong> in relation to the<br />
second pedestrian crossing <strong>and</strong> the original 6 months for completion had not yet expired.<br />
The copy of the M125/6 Track Inspection <strong>Summary</strong> <strong>Report</strong> was subsequently endorsed with<br />
the date “29/12/12” signifying that the work had been completed. It was possible that the<br />
Track Inspector had signed off the work on both pedestrian crossings as having been<br />
completed, even though the work had only been completed on one, by mistake. The close<br />
physical proximity of the pedestrian crossings, separated only by the vehicle level crossing,<br />
<strong>and</strong> their proximity on the <strong>Summary</strong> <strong>Report</strong> would tend to support this.<br />
That information was entered into the ADB on 4 January 2013. At that time the TID<br />
reference was transferred as completed from the M125/6 Track Inspection <strong>Summary</strong> <strong>Report</strong><br />
to the ADB Archive (Complete).<br />
<strong>Report</strong> on Collision Train 126 with Power Wheelchair, <strong>Morningside</strong>, 25 February 2013 Page 15