ARROW LNG PLANT<br />
Geotechnical Investigations<br />
‣ <strong>Arrow</strong> is commencing a drilling program<br />
in June 2012 with both marine and land<br />
based drilling rigs.<br />
‣ The drilling program will target the soil,<br />
rock and sediment located at the<br />
mainland launch site, cross harbour<br />
tunnel, marine facilities and LNG Plant<br />
on Curtis Island.<br />
‣ The program will assess the following:<br />
• Geotechnical properties<br />
• Acid Sulfate Soils (ASS/PSS)<br />
• Dredge sediment characterisation<br />
Jack-up Barge – <strong>Arrow</strong> Drilling Program 2010