Work, including, but not be limited to, the availability and cost of labour, applicable<br />
laws and regulations and facilities for transportation, handling and storage of<br />
materials and equipment and limitation of working days due to monsoon.<br />
It must be understood and agreed that such factors have been properly<br />
investigated and considered in the preparation of the Proposal submitted. No<br />
claims for financial and time adjustment to the Contract awarded for the Work<br />
under these Specifications and Documents will be permitted by the Board/Engineer<br />
which are based on the lack of such prior information or its affect on the cost of the<br />
work and its completion time.<br />
9.0 DEPARTURES FROM SPECIFICATIONS<br />
Tenderers shall base their Proposals on the Tender requirement. However, if they<br />
so desire, they may also submit alternate Proposals on equipment which departs<br />
from these requirement and which would, in the opinion of the Tenderer, be of<br />
benefit to the Board. The Tenderer shall state in detail the departures which he<br />
deems advisable, and how they will be of benefit to the Board. Alternate Proposals<br />
shall be accompanied by drawings showing the suggested layout and<br />
arrangements. Alternative proposal shall be a separate complete proposal with<br />
complete set of drawings, catalogues, manual, etc. without any reference to the<br />
main Proposal. Alternate proposal of only technically responsive lowest evaluated<br />
Tenderer shall be considered.<br />
10.0 INFORMATION TO BE SUPPLIED WITH THE PROPOSALS<br />
Tenderers shall supply sufficient details to permit complete evaluation of all aspects<br />
of the Proposals. Tenderers are requested not to put any clause of their own i.e.<br />
anything outside this Tender Document.<br />
The drawing showing the location and the layout recommended by the Tenderer<br />
shall also be submitted along with the Proposal. Proposals shall be in English and<br />
executed on the Tender Forms, annexed hereto, for that purpose. All the Tender<br />
Forms shall be completely and legibly filled in and all information asked for in the<br />
Tender Documents shall be furnished.<br />
11.0 TIME SCHEDULE<br />
The Construction Schedule in the Tender Documents for performing the specified<br />
work will be a basic consideration of the Contract. The construction schedule<br />
shows the period in calendar days for completion of the Power Plant as desired by<br />
the Board and the estimated equipment delivery and erection time that will be<br />
required to meet this period for completion.<br />
The Tenderer shall furnish with his Proposal, Time Schedule showing the respective<br />
times for manufacture, shipment from shop to the Site, erection, preliminary<br />
testing, trial operation and performance testing for complete Power Plant included<br />
in his Proposal.<br />
Ghorasal 200 MW -300 MW Gas Turbine Peaking Power Plant Project 2nd Re-tender (Vol-1 of 3)<br />