g. Discount rate on capital investment - 15%<br />

(iv)<br />

Example of Financial Analysis on Natural Gas:<br />

(Analysis will be made on both HSD and Natural Gas)<br />

(1) Po = Total Net generated output at generator terminals at Site Condition in kW<br />

EP 0 = Annual generated energy at generator terminals in Kwh<br />

= P 0 x 24 x 365 x 0.3 Kwh<br />

H = Average weighted heat rate of generating unit<br />

(100%, 75% and 50% load at Site Condition) in KJ / kWH<br />

= H 100% x 0.7 + H 75% x 0.2 + H 50% x 0.1 KJ per Kwh<br />

Hc = Annual heat consumption<br />

= H x EP 0 in KJ<br />

Fuel Calorific Value (LHV) of Gas fc = 35,350 kJ/Nm 3<br />

Annual fuel consumption =H c / f c , Nm 3 = F a<br />

F AC = Annual fuel cost = Tk 2.82 × F a<br />

Ca = Annual operating and maintenance cost = Tk 0.20 x EP 0<br />

(2) A= First cost including the cost of essential spares as described in the Tender<br />

Documents, converted into Taka by applying the Exchange Rate as specified.<br />

(3) d = Discount rate<br />

= 15% per annum<br />

(4) D= Estimated weighted days for completion of the power plant<br />

= 600 days<br />

MD = Monetization for each day of late commissioning of the power plant<br />

= 0.1% of Tender price (first cost) per day<br />

Total Monetization, M = MD x (D1- D)<br />

= MD x (D1 - 600)<br />

(5) C T = Capitalised cost of transformer loss<br />

= [(1+r) n –1] × t × e (P 0 +0.44 P FL )<br />

r (1+r) n<br />

where, C T = Capitalised cost of transformer loss in Bangladesh Taka<br />

r = Discount rate, 15%<br />

n = Years of service life,15 years<br />

t = Operating hours in a year, 8760 hours<br />

e = Cost of energy, Taka 2.38 per Kwh<br />

P 0 = No load loss in KW<br />

P FL = Full load loss at ONAF condition in KW<br />

Ghorasal 200 MW -300 MW Gas Turbine Peaking Power Plant Project 2nd Re-tender (Vol-1 of 3)<br />