4.3.2.7 Lubricating Oil System<br />
The lubrication system <strong>of</strong> the unit shall be equipped with the main oil pump,<br />
auxiliary motor driven oil pumps, delivery pipes, return pipes, reservoir,<br />
strainer, oil cooler, pressure gauges and thermometers, and all necessary<br />
oil piping <strong>for</strong> the system.<br />
The unit shall be equipped with a gear driven main oil pump, a full capacity<br />
motor driven auxiliary oil pump and an emergency DC motor driven oil<br />
pump. The emergency DC motor driven oil pump shall have sufficient<br />
capacity to prevent damage the turbine generator during an emergency<br />
shutdown. Each oil pump shall be equipped with a section strainer.<br />
Pressure switches shall be provided as required to permit automatic<br />
sequential starting <strong>of</strong> the auxiliary oil pump, and emergency DC oil pump in<br />
case <strong>of</strong> oil pressure drop. Auxiliary contacts required <strong>for</strong> indication shall<br />
also be furnished on pumps and pressure switches.<br />
Each oil reservoir shall be furnished complete with, vapour extractor, level<br />
indicator, high and low level alarm switches, strainer, drain valves, overflow<br />
pipe, manhole, valves, and piping.<br />
The system shall include oil pressure and temperature alarm, and trip<br />
mechanism, each bearing shall be provided with thermocouple cell and a<br />
thermometer in pocket <strong>of</strong> oil drain.<br />
Complete oil coolers each <strong>for</strong> 100% capacity shall be provided. One <strong>of</strong> two<br />
oil coolers shall normally be in service, change over from one oil cooler to<br />
the other during operation shall be possible. It shall also be possible to use<br />
both oil coolers at same time. The oil coolers shall be <strong>of</strong> either air cooling<br />
type or water cooling type. The oil coolers shall be provided with blowers or<br />
water pumps, depending upon the type <strong>of</strong> cooling.<br />
4.3.2.8 Natural Gas Fuel System<br />
The unit shall be provided with gas fuel system. The natural gas system<br />
shall have the necessary pressure regulating valves, piping, shut <strong>of</strong>f valves,<br />
metering device, pressure gauges, and other indicating instruments<br />
including flow meter with integration. The gas fuel system shall be provided<br />
with necessary protective equipment <strong>for</strong> proper control and safe operation<br />
<strong>of</strong> the gas turbine generating unit.<br />
Specification <strong>of</strong> Natural Gas has been furnished in Annexure -1. The<br />
system shall comprise at least, the following major items including gas<br />
booster compressor:<br />
- Shut <strong>of</strong>f valve.<br />
- An inlet strainer.<br />
- A flow-meter with bypass system.<br />
- Pressure regulating equipment.<br />
- Pressure gauges on be<strong>for</strong>e and after regulating equipment.<br />
- A gas conditioner (scrubber and demister).<br />
- A knock out drum if required.<br />
- Drain tank.<br />
- Flare system.<br />
- Inert gas purging system<br />
<strong>Ghorasal</strong> <strong>300</strong>-<strong>450</strong> <strong>MW</strong> CCPP Project (Vol-2A <strong>of</strong> 2) 48