View as PDF - Rail Professional
View as PDF - Rail Professional
View as PDF - Rail Professional
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
BUSINESS PROFILE<br />
Movable access speeds<br />
King’s Cross project<br />
While working on a contract to install permanent<br />
walkways and gantries on the refurbished roof,<br />
Allystructures saw how the need to constantly erect<br />
and dismantle steel scaffolding w<strong>as</strong> slowing down the<br />
installation of the new glazing installation work.<br />
The Chester-b<strong>as</strong>ed fabricator supplied a system – known on site<br />
<strong>as</strong> the ‘flying carpet’ – that comprised independently movable access<br />
platforms at four different levels under the roof at King’s Cross.<br />
The bespoke platforms were individually shaped to the contour<br />
of the building and moved using Allystructures unique track design.<br />
The innovative access system allowed the installers of the new roof,<br />
gl<strong>as</strong>s and photovoltaic solar power panels to operate 24 hours a day,<br />
seven days a week (twice <strong>as</strong> f<strong>as</strong>t <strong>as</strong> previously), resulting in a rapid<br />
acceleration in the construction programme.<br />
Each platform provided a 30 metre long working area at each<br />
level. Once work had been completed on a section of the roof, the<br />
platforms were e<strong>as</strong>ily moved to the next position and available for<br />
immediate work (the platforms also allow multiple teams to work<br />
at the same time, making the workplace more accessible and the<br />
site tidier and safer, because there is no need to store and move steel<br />
scaffolding tubes and fittings).<br />
The glazing work w<strong>as</strong> part of a major project to refurbish the roof<br />
– Kier Construction w<strong>as</strong> the main contractor for Network <strong>Rail</strong>. This<br />
called for Kier to strip out the existing roof, grit bl<strong>as</strong>t, make good and<br />
paint the steel structure, then install the new glazing and solar panels.<br />
It also included the installation of a permanent walkway and gantry<br />
system by Allystructures.<br />
Paul Butt of Allystructures explains: ‘Kier’s open approach to<br />
working with its contractors allowed me to suggest improvements to<br />
the access requirements; I could see the benefit of creating multiple<br />
work faces, reducing the downtime and improving the work flow of<br />
the gl<strong>as</strong>s installation.’<br />
To reach each section of the roof the glaziers had to erect steel<br />
scaffolding on top of the suspended access deck.<br />
The whole roof is 40 bays long and between April and August<br />
2011 only 12 bays had been completed. After Allystructures installed<br />
the ‘flying carpet’ in November 2011, a further 13 bays were<br />
completed in a period of just eight weeks.<br />
Construction’s project manager Simon Matthews comments:<br />
‘With the traditional glazing scaffolding we were spending more<br />
time erecting the scaffold than the glaziers used it. We developed<br />
the flying carpet with Allystructures to save time and cost on this<br />
high profile project. The platforms provided a safe and clear working<br />
area on which the glaziers were able to work at a much improved<br />
efficiency.’ Allystructures overcame difficult design challenges and<br />
delivered the project on a very tight schedule.<br />
For further information contact Aluminium Structures (Work Platforms) Ltd.<br />
Tel: +44 (0)1244 531 889<br />
Email: info@allystructures.co.uk Web: www.allystructures.co.uk<br />
Page 32 september 2012