Fort Berthold Development Plans<br />
B<br />
1280 acres<br />
TF B TF<br />
1320’ 1320’ 1320’<br />
• Maximize long horizontals<br />
• Develop from pads: 2 Bakken/2 Three Forks<br />
• Tie in as soon as possible<br />
• Test inter-well spacing<br />
• Work with other operators to time development<br />
• Reduce cycle time to 45 days from rig release<br />
of final well on pad to production<br />
• Implement salt water disposal solution<br />
• Understand and successfully implement<br />
simultaneous operations<br />
TF B B TF<br />
1280 acres<br />
• Drilling and completion of additional wells<br />
on producing pads<br />
48