Marcellus Well Timeline<br />
6 – 8 months<br />
Well application / permit<br />
approval<br />
Site Build<br />
Drilling<br />
Waiting on Frac<br />
Crews<br />
Fracing<br />
45 – 60 days in PA<br />
45 – 90 days<br />
25 – 35<br />
days/well<br />
30 - 60 days<br />
7 - 14 days<br />
• 30 – 45 days in WV<br />
• Assumes water sources<br />
permitted<br />
• Current regulations<br />
• Cannot begin<br />
building site<br />
until permit in<br />
hand<br />
• Depends on<br />
time of year<br />
• Multi-well<br />
pads<br />
• “self-skidding”<br />
rigs help<br />
reduce drilling<br />
time<br />
• Shortage of<br />
frac fleets<br />
relative to<br />
basin-wide<br />
drilling activity<br />
Note: Timeline excludes well “resting” and tie-in to gathering systems<br />
71