Polaris<br />

Engineering<br />

Standard<br />

430.1<br />

Rev.: 0<br />

Page: 4 of 9<br />

Date: 07/07/09<br />

V. MIXING AND PLACING<br />

A. Job-Mixed Concrete<br />

1. Job-mixed concrete shall be in accordance with ACI 304R.<br />

2. Rotate the mixer at a speed recommended by the mixer manufacturer.<br />

Continue mixing for at least 1-1/2 minutes after all materials are in the<br />

mixer.<br />

3. Mix all concrete until there is a uniform distribution of the materials and<br />

discharge completely before recharging the mixer.<br />

B. Ready-Mixed Concrete<br />

Mix and deliver Ready-mixed concrete in accordance with ASTM C94.<br />

C. Placing Concrete<br />

1. Deposit concrete as near as practical to its final position to avoid<br />

segregation of aggregates due to rehandling or flowing. The concrete<br />

must be plastic at all times and flow readily into the spaces between<br />

reinforcing bars. Water in excess of approved batch quantities shall not be<br />

added for this purpose; however, appropriate admixtures approved by the<br />

Client and/or Polaris Engineering may be used to improve flow.<br />

2. After concrete placement has started, continue operation until the section<br />

is completed except as prohibited or permitted by Section VI.<br />

3. Do not drop concrete vertically more than eight feet. Use drop chutes for<br />

higher lifts. The chute shall have a diameter of at least eight times the<br />

maximum aggregate size and shall be positioned so that the concrete will<br />

drop vertically.<br />

4. Do not start placing concrete in supported elements (beams or slabs) until<br />

the concrete previously placed in columns or walls is no longer plastic and<br />

has been in place at least two hours.<br />

5. All concrete shall be thoroughly consolidated by suitable means during<br />

placement, and shall be thoroughly worked around the reinforcement and<br />

embedded items and into the corners of the forms.<br />

6. Install all embedded items such as anchor bolts, sleeves, inserts,<br />

equipment bed and slide plates in their correct location and secure against<br />

displacement.