Express Plan Check/Permit Process<br />
• Scheduled meeting with SCCO Building Inspection Office with<br />
the goal of receiving permit pending no plan check comments<br />
• Applicable to small projects with no complexity in scope:<br />
• Door installation<br />
• Small renovation within a building<br />
• Moving of walls involving minor mechanical/electrical<br />
• Requires SUFMO review <strong>and</strong> stamp on plans prior to submitting<br />
to County<br />
• Submit 3 complete sets of plans<br />
• Call Building Inspection Office to schedule appointment<br />
• If permit is not granted, average review time is 1-2 weeks<br />