<strong>Dakshin</strong> <strong>Gujarat</strong> <strong>Vij</strong> <strong>Company</strong> <strong>Limited</strong><br />
Truing up for FY 2010-11<br />
and Determination of Tariff for FY 2012-13<br />
water irrigation, the same cannot be extended for lifting water from ground water<br />
sources.<br />
Commission’s View: The consumers are broadly categorised based on end use<br />
and tariffs are determined accordingly.<br />
10. Night hour concessional tariff<br />
Objection: Some of the stakeholders have stated that the night hour benefit should<br />
be given on all units like peak hour units recovery.<br />
Response of the Licensee: The licensee has submitted that the cost of supplying<br />
power at peak hours is significantly high. Thus, tariff structure is devised recognizing<br />
this fact and allowing recovery at higher rates for peak hour use. Moreover, the<br />
objective of giving night benefit to the consumer is to shift their demand to off peak<br />
hours and thereby to help the grid as well as to flatten the demand curve of the utility.<br />
But the consumers who otherwise consume energy throughout the day or as a part of<br />
their process they consume power during night hours cannot be considered to have<br />
made additional efforts to shift the load from peak hrs. Therefore, the night hours<br />
concession is given on the energy consumption during night hours in excess of one<br />
third of the total energy consumption of a particular month.<br />
Commission’s View: It is true that night time consumers facilitate the reduction of<br />
peak demand, by shifting their demand to off peak period. They allow the base load<br />
equipment to be loaded optimally. The night hour concessional tariff can be extended<br />
to those consumers who have shifted significant quantum of consumption from peak<br />
hours to night hours.<br />
11. Applicability of Demand Charges on Night Tariff<br />
Objection: Some of the stakeholders have stated that the night tariff should not have<br />
any demand charge. During the night demand is low and, therefore, the infrastructure<br />
is sub-optimally loaded. The fixed cost refers to peak cost.<br />
Response of the Licensee: The licensee has submitted that the fixed charges are<br />
levied from the consumer to recover company‟s fixed cost which the company will<br />
incur irrespective of consumption and time of consumption by the consumer. Fixed<br />
charges mainly cover cost components like cost of infrastructure, employee cost,<br />
<strong>Gujarat</strong> Electricity Regulatory Commission Page 18<br />
June 2012