09.01.2015 Views

Downloads - Pile Driving Contractors Association

Downloads - Pile Driving Contractors Association

Downloads - Pile Driving Contractors Association

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Project Spotlight<br />

Huntingdon Place<br />

When Toll Brothers, Inc. purchased a parcel of land<br />

in Huntingdon Valley, Pa., it envisioned a luxury<br />

condominium complex with picturesque views<br />

of the adjoining creek and wooded areas. The severe sloping<br />

of the property, however, and the fact that 75 percent<br />

of the parcel was below the 100-year floodplain elevation,<br />

presented design and construction challenges that would<br />

require creativity to realize the vision that the Toll team<br />

had created.<br />

The first task in accomplishing the goal was to arrange<br />

the site so that residential living could occupy the site and<br />

not have any concerns about potential flooding. The solution<br />

was to create a detention basin and lake area that would<br />

have the capacity to contain storm events and still allow<br />

enough area to provide adequate residential living space.<br />

Doing so would require the construction of a retaining wall<br />

around 80 percent of the site and the cut and fill of 100,000<br />

cubic yards of material. The second task was to determine<br />

how best to support the proposed structure, which consisted<br />

of five total levels with the first level dedicated as an atgrade<br />

parking level under an elevated podium slab and the<br />

remainder of residential living space.<br />

The owner’s design team determined that given the<br />

poor soil conditions and the need for a grade separation wall<br />

between the building footprint and the retention basin, a<br />

precast segmental concrete wall would be used to support the<br />

embankment and auger cast piles would be used to support<br />

the structure. When original budget pricing was received<br />

from several contractors, the estimated construction costs<br />

far exceeded the client’s budget and nearly scrapped the<br />

project.<br />

One of the contractors that submitted budget pricing was<br />

PDCA member Loftus Construction, Inc. of Cinnaminson,<br />

N.J. When notified by Toll that the project was grossly over<br />

budget, that construction time far exceeded the anticipated<br />

opening date and the project was in peril of being shelved,<br />

Loftus requested the opportunity to present value engineering<br />

solutions.<br />

Having been granted the time by Toll to evaluate value<br />

engineering solutions, Loftus engaged the services of Pierce<br />

Engineering, Inc., the pre-eminent foundation design firm in<br />

the Delaware Valley and a PDCA member firm. The team<br />

then sought to pinpoint critical components of the project<br />

that were driving the costs and schedule, and how to best<br />

minimize the impact of those components. The single largest<br />

factor driving the cost and schedule was the poor soil conditions.<br />

The design team’s selection of the precast concrete<br />

wall was well suited for the soil conditions, but would require<br />

the export of nearly 40,000 CY of material excavated for the<br />

wall and the import of clean stone.<br />

Loftus, after careful consideration of several options,<br />

proposed a contractor designed steel sheet pile wall that was<br />

tied back with a reinforced concrete deadman system. This<br />

system was chosen for many reasons. It was cost effective<br />

compared to other solutions due to the curving geometry of<br />

the structure, and multiple changes in direction of the proposed<br />

wall layout which is 1,100 feet long and 30 feet high.<br />

Specifically, the wall was constructed of PZ27 sheets with a<br />

coal tar epoxy coating. Double C12x30 members were used<br />

as walers and a 1¼” grade 50, epoxy coated threadbar was<br />

used as tiebacks to the reinforced concrete deadmen. The<br />

deadman was situated such that bearing pile installation<br />

could follow the sheeting without affecting the tiebacks.<br />

The proposed system drastically reduced the overall cost<br />

of the perimeter wall by eliminating the structural excavation<br />

for the segmental wall and eliminating the need for a<br />

costly wellpoint dewatering system as all of the structural<br />

excavation was below the groundwater level. The proposed<br />

system also reduced the cost of the earthwork package by<br />

eliminating the export of 40,000 CY and the import of the<br />

clean stone. An additional benefit of the value engineering<br />

design is the elimination of staged earthwork further reduc-<br />

• Q4 • 2008<br />

51

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!