M2 / M3 Development &<br />

Procurement Plan<br />

M2 and M3 Production begins October 2011<br />

<strong>TMT</strong> anticipates:<br />

– 12 month Preliminary Design Phase (PDP)<br />

– Final Design (12 months)<br />

– Fabrication, Integration & Testing (~ 4 years)<br />

– Shipment to the summit and AIV (2 months)<br />

M3 Schedule same<br />

<strong>TMT</strong>.OPT.PRE.09.099.DRF03 36