20.01.2015 Views

2012 Annual Report (2 April 2013) - Grange Resources

2012 Annual Report (2 April 2013) - Grange Resources

2012 Annual Report (2 April 2013) - Grange Resources

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

18<br />

PAGE<br />

<strong>2012</strong> ANNUAL REPORT<br />

Review of Operations (cont.)<br />

SOUTHDOWN MAGNETITE PROJECT<br />

The Southdown Project ultimately aims to export 10 million tonnes per year of magnetite<br />

concentrate to Asian steel markets. The Southdown Joint Venture (SDJV) is a joint<br />

venture between <strong>Grange</strong> <strong>Resources</strong> Ltd (70%) and SRT Australia Pty Ltd (SRTA) (30%).<br />

SRTA is jointly owned by Sojitz Corporation, a Japanese global trading company, and<br />

Kobe Steel, Japan’s third largest steel producer.<br />

Key <strong>2012</strong> Achievements<br />

◆◆<br />

◆◆<br />

◆◆<br />

◆◆<br />

◆◆<br />

Completed a definitive feasibility study in <strong>April</strong> <strong>2012</strong> which improved the project’s<br />

level of accuracy to +/- 15%<br />

Progressed project engineering, land acquisition, permitting, drilling and test work<br />

Initial capital expenditure estimated at A$2.885 billion (including EPCM; owners’<br />

costs and contingency of $0.535 billion)<br />

Operating costs estimated at A$58.5 per tonne of premium quality concentrate<br />

(69.6% fe) containing low contaminants (excl. royalties)<br />

Submission by EPC contract tenders for major construction works by interested<br />

parties<br />

During <strong>2012</strong> the Definitive Feasibility Study (DFS) for the Project was finalised and<br />

subsequently reviewed by an independent Technical Due Diligence Engineering firm<br />

which did not identify any fatal factors in the Southdown Feasibility Study.<br />

During <strong>2012</strong> Engineering, Procurement and Construction (EPC) tenders were issued to<br />

the market for major project packages. The tenders received from this process were<br />

analysed and evaluated in detail with recommendations to shortlist tenderers issued to<br />

the Owners.<br />

Significant milestones were achieved in the environmental area with Section 38 Approval<br />

for the Desalination Plant received on 18 July <strong>2012</strong> when the Minister for the Environment<br />

signed Ministerial Statement 904. Environmental Management Plans were also<br />

submitted to relevant government agencies and stakeholders during September <strong>2012</strong>.<br />

<strong>Grange</strong> announced to the market on 29 November <strong>2012</strong> that it would significantly<br />

reduce expenditure on its 70% share of the Southdown Magnetite Project. Following this<br />

announcement the Project’s team size and scope of work has been reduced.<br />

<strong>2013</strong> Project Priorities<br />

◆◆<br />

◆◆<br />

◆◆<br />

Continue search for new equity partner to take a strategic share of the Company’s<br />

interest<br />

Significantly reduce expenditure for <strong>2013</strong> to approx. $2.5 million (<strong>Grange</strong> share)<br />

Maintain all tenements, permits and project assets in good order<br />

<strong>Grange</strong> has the in house skills, systems, capability and discipline to deliver Southdown’s<br />

potential when the time is right<br />

Project Overview<br />

Geology and Resource<br />

The Southdown magnetite deposit is a<br />

long, thin, near-surface, continuous ore<br />

body. It extends over 12 kilometres, with<br />

depths varying from 50 metres in the west<br />

to 480 metres in the east.<br />

The deposit has been drilled and<br />

evaluated since its initial discovery in<br />

1983, including an extensive program<br />

of resource drilling during 2011 for the<br />

feasibility study. A resource model update<br />

was completed in December <strong>2012</strong> for<br />

the deposit, significantly increasing the<br />

quality and confidence in the resource.<br />

The Southdown resource now exceeds<br />

1.2 billion tonnes.<br />

Conventional Mining<br />

Targeted concentrate production rates<br />

require a material movement in the mine of<br />

up to 132 Mt per annum by conventional<br />

drill, blast, load and haul mining methods.<br />

The final proposed pit is six kilometres<br />

long, one kilometre wide and about 370<br />

metres deep. The mining operation<br />

will draw heavily on <strong>Grange</strong>’s existing<br />

capability as Australia’s most experienced<br />

commercial producer of magnetite<br />

concentrate, to assist with start-up and<br />

ongoing operations.<br />

Ore crushing and Concentration<br />

The project plan envisages Southdown<br />

ore being processed to increase the<br />

iron content from around 25% to 69%.<br />

Extensive metallurgical test work including<br />

pilot plant trials have been conducted<br />

since 2004. The process includes<br />

crushing, grinding, classification and<br />

magnetic separation. The concentrate is<br />

further upgraded using hydro separation<br />

to remove fine silica, and flotation to<br />

remove sulphur impurities.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!