2012 Annual Report (2 April 2013) - Grange Resources
2012 Annual Report (2 April 2013) - Grange Resources
2012 Annual Report (2 April 2013) - Grange Resources
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
18<br />
PAGE<br />
<strong>2012</strong> ANNUAL REPORT<br />
Review of Operations (cont.)<br />
SOUTHDOWN MAGNETITE PROJECT<br />
The Southdown Project ultimately aims to export 10 million tonnes per year of magnetite<br />
concentrate to Asian steel markets. The Southdown Joint Venture (SDJV) is a joint<br />
venture between <strong>Grange</strong> <strong>Resources</strong> Ltd (70%) and SRT Australia Pty Ltd (SRTA) (30%).<br />
SRTA is jointly owned by Sojitz Corporation, a Japanese global trading company, and<br />
Kobe Steel, Japan’s third largest steel producer.<br />
Key <strong>2012</strong> Achievements<br />
◆◆<br />
◆◆<br />
◆◆<br />
◆◆<br />
◆◆<br />
Completed a definitive feasibility study in <strong>April</strong> <strong>2012</strong> which improved the project’s<br />
level of accuracy to +/- 15%<br />
Progressed project engineering, land acquisition, permitting, drilling and test work<br />
Initial capital expenditure estimated at A$2.885 billion (including EPCM; owners’<br />
costs and contingency of $0.535 billion)<br />
Operating costs estimated at A$58.5 per tonne of premium quality concentrate<br />
(69.6% fe) containing low contaminants (excl. royalties)<br />
Submission by EPC contract tenders for major construction works by interested<br />
parties<br />
During <strong>2012</strong> the Definitive Feasibility Study (DFS) for the Project was finalised and<br />
subsequently reviewed by an independent Technical Due Diligence Engineering firm<br />
which did not identify any fatal factors in the Southdown Feasibility Study.<br />
During <strong>2012</strong> Engineering, Procurement and Construction (EPC) tenders were issued to<br />
the market for major project packages. The tenders received from this process were<br />
analysed and evaluated in detail with recommendations to shortlist tenderers issued to<br />
the Owners.<br />
Significant milestones were achieved in the environmental area with Section 38 Approval<br />
for the Desalination Plant received on 18 July <strong>2012</strong> when the Minister for the Environment<br />
signed Ministerial Statement 904. Environmental Management Plans were also<br />
submitted to relevant government agencies and stakeholders during September <strong>2012</strong>.<br />
<strong>Grange</strong> announced to the market on 29 November <strong>2012</strong> that it would significantly<br />
reduce expenditure on its 70% share of the Southdown Magnetite Project. Following this<br />
announcement the Project’s team size and scope of work has been reduced.<br />
<strong>2013</strong> Project Priorities<br />
◆◆<br />
◆◆<br />
◆◆<br />
Continue search for new equity partner to take a strategic share of the Company’s<br />
interest<br />
Significantly reduce expenditure for <strong>2013</strong> to approx. $2.5 million (<strong>Grange</strong> share)<br />
Maintain all tenements, permits and project assets in good order<br />
<strong>Grange</strong> has the in house skills, systems, capability and discipline to deliver Southdown’s<br />
potential when the time is right<br />
Project Overview<br />
Geology and Resource<br />
The Southdown magnetite deposit is a<br />
long, thin, near-surface, continuous ore<br />
body. It extends over 12 kilometres, with<br />
depths varying from 50 metres in the west<br />
to 480 metres in the east.<br />
The deposit has been drilled and<br />
evaluated since its initial discovery in<br />
1983, including an extensive program<br />
of resource drilling during 2011 for the<br />
feasibility study. A resource model update<br />
was completed in December <strong>2012</strong> for<br />
the deposit, significantly increasing the<br />
quality and confidence in the resource.<br />
The Southdown resource now exceeds<br />
1.2 billion tonnes.<br />
Conventional Mining<br />
Targeted concentrate production rates<br />
require a material movement in the mine of<br />
up to 132 Mt per annum by conventional<br />
drill, blast, load and haul mining methods.<br />
The final proposed pit is six kilometres<br />
long, one kilometre wide and about 370<br />
metres deep. The mining operation<br />
will draw heavily on <strong>Grange</strong>’s existing<br />
capability as Australia’s most experienced<br />
commercial producer of magnetite<br />
concentrate, to assist with start-up and<br />
ongoing operations.<br />
Ore crushing and Concentration<br />
The project plan envisages Southdown<br />
ore being processed to increase the<br />
iron content from around 25% to 69%.<br />
Extensive metallurgical test work including<br />
pilot plant trials have been conducted<br />
since 2004. The process includes<br />
crushing, grinding, classification and<br />
magnetic separation. The concentrate is<br />
further upgraded using hydro separation<br />
to remove fine silica, and flotation to<br />
remove sulphur impurities.