<strong>Whittier</strong> <strong>Bridge</strong>/I-<strong>95</strong> Improvement Project FEIR<br />
Chapter 1.0: Changes Since the Draft <strong>Environmental</strong> <strong>Impact</strong> <strong>Report</strong> and Resolution of Additional Issues<br />
Table 1-3:<br />
Riverfront Area Mitigation – Newburyport<br />
Existing<br />
<strong>Impact</strong> Estimates<br />
(sf)<br />
Area of Riverfront on Site 356,000<br />
<strong>Impact</strong>ed<br />
Areas (sf)<br />
Areas<br />
Subject to<br />
RFA<br />
Mitigation<br />
(sf)<br />
Existing Degraded 22,925 N/A<br />
Previously Developed<br />
(Engineered Sideslopes) 13,614 13,614<br />
Undisturbed 1,060 N/A<br />
Total 37,599 13,614<br />
Temporary <strong>Impact</strong>ed<br />
Riverfront (Undisturbed) 4,770 N/A<br />
Mitigation Rationale<br />
Mitigation not required for redevelopment of<br />
Existing Degraded areas.<br />
Previously Developed areas (i.e. Engineered<br />
Side Slopes / Previously Graded Areas) may<br />
require mitigation under 310 CMR 10.58(5)(e)<br />
Does not require mitigation under 310 CMR<br />
10.58(4)(d)1, though undisturbed impacts<br />
cannot cumulatively exceed 10% of RFA on the<br />
lot.<br />
Does not require mitigation under 310 CMR<br />
10.58(4)(d)1, though undisturbed impacts<br />
cannot cumulatively exceed 10% of RFA on the<br />
lot. The 4,770 s.f. of temporary impacts will be<br />
mitigated through "in kind" or in situ restoration.<br />
Temporary <strong>Impact</strong>ed<br />
* Temporary <strong>Impact</strong>s will be mitigated through<br />
Riverfront (Previously<br />
"in kind" or in situ restoration, and are therefore<br />
Developed) 15,590 * not included in the mitigation calculation below.<br />
Overall Total 57,<strong>95</strong>9 0 Includes permanent and temporary impacts<br />
Mitigation Calculations<br />
10% of total RFA 35,600<br />
Existing Degraded 22,925<br />
Difference between 10% of<br />
site and Existing Degraded<br />
= additional allowed<br />
alteration without mitigation 12,675<br />
Area Of Permanent<br />
Previously Developed<br />
<strong>Impact</strong>s 13,614<br />
Required Mitigation under<br />
310 CMR 10.58(e) 939<br />
Proposed Restoration<br />
Area for Permanent<br />
<strong>Impact</strong>s 12,200<br />
Proposed Restoration for<br />
Temporary <strong>Impact</strong>s 20,360<br />
Total Mitigation 32,560<br />
Note: Refer to Figure 1-7 for locations of impacted and restored areas.<br />
Proposed <strong>Impact</strong>s to permanent and temporary<br />
Undisturbed RFA must not exceed 35,600 s.f.<br />
under 310 CMR 10.58(4)(d)1. (project 29,770<br />
s.f. below threshold).<br />
The proposed work may alter up to 10% if the<br />
degraded area is less than 10% of the riverfront<br />
area on the site; 310 CMR 10.58(5)(e).<br />
The redevelopment work may impact up to<br />
12,675 s.f. without requiring Mitigation; 310<br />
CMR 10.58(5)(e).<br />
Difference between <strong>Impact</strong>s to Previously<br />
Developed RA (13,614) and additional area to<br />
achieve 10% degraded RA (12,675).<br />
Mitigation provided at an approximate 5:1 ratio<br />
for permanent impacts through restoration of<br />
existing degraded areas.<br />
Mitigation provided at 1:1 ratio for temporary<br />
impacts (15,590 s.f + 4,770 s.f.)<br />
Permanent <strong>Impact</strong> Mitigation + Temporary<br />
<strong>Impact</strong> Mitigation.<br />
1-20