Options considered<br />
Detailed Cost Estimate Examples<br />
WISSAHICKON SCHOOL DISTRICT<br />
MATTISON AVENUE ELEMENTARY RENOVATION<br />
June 30, 2011<br />
Description<br />
Renovate existing facility.<br />
WISSAHICKON SCHOOL DISTRICT<br />
SHADY GROVE ELEMENTARY RENOVATION<br />
June 30, 2011<br />
Description<br />
Renovate existing facility adding capacity for underutilized areas. Expand the Kitchen onto the<br />
cafeteria and expand the cafeteria into the stage.<br />
Summary of Construction Costs<br />
New Construction<br />
Building $0<br />
Sitework $800,000<br />
Renovation<br />
Renovate Existing Building (28,000 sf x $150) $4,200,000<br />
Architectural and Engineering Fees $300,000<br />
Land Development Engineering Fees $200,000<br />
Movable Equipment Cost $150,000<br />
Sub-Total $5,650,000<br />
Additional Construction Related Costs<br />
Additional Construction Related Costs (includes geo-technical and<br />
environmental reports, site surveys, agency approval fees,<br />
printing, project management fees including construction<br />
supervision, miscellaneous expenses and contingency) $1,130,000<br />
Financing Costs (including bond discount, legal fees,<br />
financial advisor, and printing) $300,000<br />
$1,430,000<br />
Estimated Project Cost $7,080,000<br />
Cost estimates are exclusive of the following:<br />
Sanitary system upgrades, hazardous material removal, and off-site upgrades.<br />
Summary of Construction Costs<br />
New Construction<br />
Building $0<br />
Sitework $1,500,000<br />
Renovation<br />
Renovate Existing Building (91,000 sf x $130) $11,830,000<br />
Architectural and Engineering Fees $799,800<br />
Land Development Engineering Fees $200,000<br />
Movable Equipment Cost $399,900<br />
Sub-Total $14,729,700<br />
Additional Construction Related Costs<br />
Additional Construction Related Costs (includes geo-technical and<br />
environmental reports, site surveys, agency approval fees,<br />
printing, project management fees including construction<br />
supervision, miscellaneous expenses and contingency) $2,945,940<br />
Financing Costs (including bond discount, legal fees,<br />
financial advisor, and printing) $300,000<br />
$3,245,940<br />
Estimated Project Cost $17,975,640<br />
Cost estimates are exclusive of the following:<br />
Sanitary system upgrades, hazardous material removal, and off-site upgrades.<br />
BRESLIN RIDYARD FADERO ARCHITECTS<br />
DHUY Engineering, Inc.