<strong>Ecological</strong> <strong>Management</strong> <strong>Plan</strong> <strong>for</strong><br />
<strong>LNG</strong> <strong>Facility</strong> <strong>Preclearing</strong> Activities<br />
September 2010<br />
Role<br />
Responsibility<br />
Supervise clearing works and ensure impacts on flora and fauna are<br />
minimised to the greatest extent practical, in accordance with<br />
commitments, guidelines and mitigation measures outlined in this<br />
<strong>Ecological</strong> <strong>Management</strong> <strong>Plan</strong>, as amended.<br />
Liaise with Queensland Parks and Wildlife about suitable relocation<br />
sites <strong>for</strong> fauna on Curtis Island<br />
Obtain necessary approvals <strong>for</strong> fauna handling<br />
Provide advice to the EPC Contractor/Proponent during<br />
environmental incidents<br />
Other Contractors/ Sub-contractors<br />
Ensure all specifications are met in accordance with the lead<br />
contractor‘s or Proponent‘s guidelines/work requirements/legal<br />
obligations as outlined in this <strong>Ecological</strong> <strong>Management</strong> <strong>Plan</strong>.<br />
7.2 Key Actions and Timing<br />
Key actions, timing and division of responsibility during preclearing activities (i.e. activities prior to tree<br />
felling/vegetation clearing and grubbing) are highlighted in the tables below.<br />
Table 13: Actions and Timing Associated with <strong>Preclearing</strong> Activities – <strong>QGC</strong><br />
Action Specifications Timing<br />
Arrange ecologists/fauna<br />
specialists<br />
Nominate local fauna<br />
handlers/carers<br />
Conduct spot HSSE and<br />
technical audits (where<br />
necessary)<br />
Generate weekly report<br />
Arrange ecologists/fauna specialists <strong>for</strong> all preclearing<br />
activities. Note: once on site, ecologists/fauna specialists<br />
will be under the management/supervision of the EPC<br />
contractor and expected to abide by the same site<br />
procedures and company requirements outlined in the<br />
project execution plan and various HSSE plans<br />
Provide EPC Contractor with details local veterinarians,<br />
registered wildlife carers/rescue organisations, and snake<br />
handlers<br />
Audits will be conducted to ensure on site activities are<br />
conducted in accordance with the current legislation,<br />
standards, licensing conditions and procedures detailed<br />
in applicable <strong>Management</strong> <strong>Plan</strong>s<br />
<strong>QGC</strong> Site HSSE Manager to interface with Bechtel Site<br />
Manager on a daily basis and provide a weekly report to<br />
the <strong>QGC</strong> Environmental Manager (important issues to be<br />
relayed immediately).<br />
At least three (3) weeks<br />
prior to commencement<br />
of preclearing (clearing)<br />
stage<br />
Two (2) weeks prior to<br />
preclearing (clearing)<br />
stage<br />
Conducted in<br />
accordance with <strong>LNG</strong><br />
(Midstream) HSSE<br />
<strong>Management</strong> <strong>Plan</strong><br />
Weekly from<br />
commencement of<br />
preclearing<br />
(preparation) stage<br />
Table 14: Actions and Timing Associated with <strong>Preclearing</strong> Activities – EPC Contractor<br />
Action Specifications Timing<br />
Provide details of<br />
clearing/work methods +<br />
Provide latest clearing schedule to ecologists/fauna<br />
specialists to enable planning of preclearing activity.<br />
At least three (3) weeks<br />
prior to preclearing<br />
36 of 43