Incremental Model<br />

In this model we divide products in to builds, where section of product are created and<br />

tested separately. Here errors are found in requirement phase itself, user feedback is taken<br />

for each stage and code is tested after it’s written.<br />

(B) What is triple constraint triangle in project management<br />

?<br />

Figure :- 12.4 Project Management Triangle<br />

Project Management triangle is depicted as Cost,Schedule and scope.These three aspect<br />

form the sides of triangle and the customer is the center point.As customer is always<br />

concerned about Cost,Scope and Schedule , so in order to get customer satisfaction project<br />

manager should deliver all scope in propose schedule and cost.<br />

If we want to disturb any one of the legs then the other two legs get affected. Example If<br />

customer increases the scope then other two sides of the triangle also get affected a lot.<br />

Note:- During project management interview’s it’s rare that you will be asked directly about<br />

constraint triangle.But when you are asked about what are the main factors that affect<br />

customer satisfaction you can refer this triangle.<br />