Evolving grid Fenno-Skan 2 HVDC link - Fingrid
Evolving grid Fenno-Skan 2 HVDC link - Fingrid
Evolving grid Fenno-Skan 2 HVDC link - Fingrid
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
4<br />
Thyristor valves at the<br />
converter station in<br />
Rauma. At the converter<br />
station, direct current is<br />
converted to alternating<br />
current and vice versa.<br />
More than 40 per cent of<br />
additional transmission capacity<br />
Fin<strong>grid</strong> and Svenska Kraftnät, the electricity<br />
transmission system operators in Finland and<br />
Sweden respectively, signed an agreement on the<br />
construction of the <strong>Fenno</strong>-<strong>Skan</strong> 2 high-voltage<br />
direct current transmission <strong>link</strong> in February 2005.<br />
The criteria for the capital investment were<br />
straightforward:<br />
to increase the electricity transmission capacity<br />
between Finland and Sweden by 40 per cent<br />
and join the market more closely together<br />
to reduce the formation of price area differences<br />
between the two countries<br />
to reduce transmission losses in the transmission<br />
<strong>grid</strong>, and<br />
to improve the transmission reliability of the<br />
power system.<br />
Ownership and costs<br />
shared in equal proportions<br />
The <strong>Fenno</strong>-<strong>Skan</strong> 2 <strong>HVDC</strong> <strong>link</strong> with a power of<br />
800 megawatts will be completed in late 2011.<br />
Fin<strong>grid</strong> and Svenska Kraftnät share the ownership<br />
and capital expenditure costs of the interconnector,<br />
totalling approx. 315 million euros, in equal<br />
proportions.<br />
The total length of the connection is approx. 300<br />
kilometres. There are converter stations at both<br />
ends of the <strong>link</strong>, used for converting direct current<br />
to alternating current and vice versa.<br />
In Finland, the new <strong>link</strong> is connected to the<br />
transmission <strong>grid</strong> at the Rauma substation. In<br />
Sweden, the connection point to the Swedish <strong>grid</strong><br />
is the Finnböle substation built north of Stockholm.<br />
<strong>Fenno</strong>-<strong>Skan</strong> poles 1 and 2 will be operated<br />
in bipolar mode.<br />
Foremost parts of the<br />
<strong>Fenno</strong>-<strong>Skan</strong> 2 project<br />
Reinforcing the 33-kilometre Rauma–Rihtniemi<br />
direct current overhead line in Finland<br />
Modification of the Pyhämaa subsea<br />
electrode in Finland<br />
Rihtniemi–Dannebo submarine cable of 196<br />
kilometres<br />
Dannebo–Finnböle direct current overhead<br />
line of 70 kilometres in Sweden<br />
New Finnböle substation in Sweden.<br />
<strong>Fenno</strong>-<strong>Skan</strong> 2<br />
Power 800 MW at the receiving end<br />
Voltage 500 kV DC<br />
Current 1,663 A<br />
Transmission <strong>link</strong> length 299 km, of which<br />
103 km is overhead line and 196 km<br />
submarine cable<br />
Line commutated converter (LCC) <strong>HVDC</strong> <strong>link</strong><br />
Converter stations in Rauma (Finland)<br />
and Finnböle (Sweden)<br />
Co-operation project between Fin<strong>grid</strong> and<br />
Svenska Kraftnät<br />
Converter supplier: ABB AB/Sweden<br />
Project budget 315 million euros<br />
Commissioning at the end of 2011<br />
Submarine cable<br />
Type NOVA-L 500 kV 1x2,000 mm 2 Cu<br />
Conductor 2,000 mm 2 , copper<br />
Mass impregnated, non draining, paper<br />
insulated (MIND)<br />
Voltage 500 kV DC<br />
Diameter 132.2 mm<br />
Weight in air 58.1 kg/m<br />
Double armour<br />
Power 800 MW<br />
Cable supplier: Nexans Norway AS<br />
5