MUNICIPALITY OF NORTH PERTH<br />
ADDENDUM <strong>#1</strong><br />
FORMAL QUOTATION: <strong>2013</strong> URBAN ASPHALT SUPPLY AND PLACE<br />
INFORMATION TO BIDDERS<br />
SEALED QUOTATIONS, clearly marked as to contents, addressed to:<br />
Jennifer Bournon<br />
Receptionist<br />
Municipality of North Perth<br />
330 Wallace Avenue North<br />
Listowel, ON<br />
N4W 1L3<br />
Will be received until Thursday, September 26, <strong>2013</strong> at 4:00 p.m. local time.<br />
<strong>Quotation</strong>s will be opened publicly at the Municipality of North Perth, Municipal Building<br />
Thursday, September 26, <strong>2013</strong> at 4:05 p.m. local time.<br />
Page 1 of 9
Scope of Work<br />
THE CONTRACT IS FOR THE SUPPLY, APPLICATION AND COMPACTION OF HL4<br />
ASPHALT.<br />
*Please note that items 1, 2 and 3 will be prepared by the Municipality. The<br />
successful contractor must notify the Municipality two (2) full working days prior<br />
to commencement of work.<br />
Paving Work Locations:<br />
1. Rocher Road<br />
6.7m x 8.1m = 55m 2<br />
<strong>Supply</strong> and Place 60mm compacted thickness<br />
Approx. 8t of HL4<br />
2. 430 Inkerman St E<br />
2.5m x 6.5m = 16.25m 2<br />
5.5m x 6.8m = 37.4m 2<br />
<strong>Supply</strong> and Place 65mm compacted thickness<br />
Approx. 8t HL4<br />
3. 475 Albert Ave N<br />
6m x 7m = 42m 2<br />
<strong>Supply</strong> and place 55mm compacted thickness<br />
Approx. 6t HL4<br />
4. Wallace Ave N<br />
16m x 4m=64m2<br />
5m x 8m=40m2<br />
Cold plane existing asphalt 50mm<br />
<strong>Supply</strong> and place 50mm compacted thickness<br />
Approx 12t HL4<br />
5. Main St Intersection<br />
11.3m x 3.0m = 34 m 2<br />
Fine grade and proof roll existing gravel<br />
<strong>Supply</strong> and place 150mm compacted thickness<br />
Approx 12t HL4<br />
ALL WORK AND MATERIALS SHALL COMPLY WITH THE REQUIREMENTS OF<br />
CURRENT O.P.S. STANDARDS AND SPECIFICATIONS.<br />
Page 2 of 9
Hot Mix <strong>Asphalt</strong>:<br />
Prior to commencing construction, the contactor shall submit to the Municipality a mix<br />
design containing test results <strong>for</strong> Gradation, Marshall Stability, Marshall Flow, % Voids,<br />
and % VMA, all con<strong>for</strong>ming to OPSS 1150.<br />
The asphalt cement used shall be PG 58-28.<br />
HL4 will contain 5.3% A.C. minimum.<br />
Up to 25% recycled hot-mix will be allowed.<br />
All traffic control shall be the responsibility of the contractor.<br />
The contractor shall take four (4) samples total of HL4 at a time and location as<br />
determined by the Roads Foreman. The Municipality will deliver these samples to<br />
Naylor Engineering Ltd., of Kitchener, <strong>for</strong> extraction testing. This provision will be paid<br />
<strong>for</strong> by the Municipality of North Perth.<br />
Pulverization:<br />
The contractor shall schedule his operations such that placement of asphalt will take<br />
place no later than ten (10) business days following pulverization. Failure to do so shall<br />
result in a deduction of Five Hundred Dollars ($500.00) per business day from the total<br />
contract value payable to the contractor.<br />
Where existing asphalt thicknesses are greater than 150mm, an adjustment to the unit<br />
price may be negotiated. Measurement <strong>for</strong> payment will be by the square metre.<br />
Full Depth Removal<br />
The work under this section shall include the full depth removal of existing asphalt in<br />
section 5 and 10 in Scope of Work to a maximum depth of 70mm. Disposal of material<br />
at an off-site location arranged and paid <strong>for</strong> by the contractor.<br />
Measurement <strong>for</strong> payment will be by the square metre.<br />
Placement Method:<br />
Paving shall be done in a continuous manner as much as possible. The Contractor<br />
shall provide the Municipality with the method of surface asphalt handling to minimize<br />
asphalt segregation and cold longitudinal joints. No end dumping from trucks to the<br />
spreader will be allowed. A material transfer vehicle shall be used to transfer surface<br />
asphalt from the trucks to the spreader.<br />
Payment Adjustment <strong>for</strong> changes in the MTO AC Price Index:<br />
North Perth will adjust the payment to the Contractor based on changes to the Ministry<br />
of Transportation’s per<strong>for</strong>mance graded asphalt cement price index unless the<br />
Contractor opts out by notifying in writing within five business days of the award of the<br />
contract. Once the contractor has opted out of payment adjustments based on the<br />
Page 3 of 9
index, the Contractor will not be permitted to opt back in. The price index will be<br />
published monthly in the MTO Contract Bulletin and displayed on the OHMPA<br />
(www.ohmpa.org) and MTO website (www.raqs.mto.gov.on.ca). The price index will be<br />
used to calculate the amount of the payment adjustment per tonne of asphalt cement<br />
accepted into the Work.<br />
The price index will be based on the price, excluding taxes, FOB the depots in the<br />
Toronto area, of asphalt cement grade PG 58-28 or equivalent. One index will be used<br />
to establish and calculate the payment adjustment <strong>for</strong> all grades. As of July 2006 the<br />
price index <strong>for</strong> each month will reflect the average of the same month’s prices and be<br />
published on the last day of the month and be retroactively applied to HMA laid in the<br />
same month.<br />
A payment adjustment per tonne of asphalt cement will be established <strong>for</strong> each month<br />
in which paving occurs when the price index <strong>for</strong> the month differs by more than<br />
$15.00/tonne from the AC price index <strong>for</strong> the month prior to quotation opening. When<br />
the price index differential is less than $15.00/tonne, there will be no payment<br />
adjustment <strong>for</strong> that month. Payment adjustments due to changes in the price index are<br />
independent of any other payment adjustments made to hot mix quotation items.<br />
Provincial sales tax adjustment should be applied to the adjustment (either way).<br />
The payment adjustment per tonne will apply to the quantity of asphalt cement in the<br />
hot mix accepted into the Work during the month <strong>for</strong> which it is established. The<br />
payment adjustment <strong>for</strong> the month will be calculated by the following means:<br />
1 When AC Prices are Rising by more than a $15.00/tonne: the payment<br />
adjustment to be paid to the Contractor is the result of subtracting the price index <strong>for</strong> the<br />
month prior to when opening from the price index in effect when paving takes place,<br />
minus the $15.00 float, multiplied by the number of tonnes of PGAC incorporated in the<br />
mix(s) as determined by the job mix <strong>for</strong>mula. HST on the adjustment will be included.<br />
2 When AC Prices are Falling by more than $15.00/tonne: the payment<br />
adjustment made in favour of the Owner is the result of subtracting the price index in<br />
effect when paving takes place, plus the $15.00 float from the price index <strong>for</strong> the month<br />
prior to the quotation opening, multiplied by the number of tonnes of PGAC incorporated<br />
in the mix(s) as determined by the job mix <strong>for</strong>mula. HST on the adjustment will be<br />
included.<br />
The quantity of new asphalt cement includes all grades of asphalt cement supplied<br />
by the Contractor with and without polymer modifiers. For each month in which a<br />
payment adjustment has been established, the quantity of the escalation/deescalation<br />
will be calculated using the hot mix quantity accepted into the Work and its<br />
corresponding asphalt cement content as required by the job mix <strong>for</strong>mula.<br />
For mixes which contain reclaimed asphalt pavement, the increase due the contractor<br />
or the rebate due the owner will be calculated as if virgin hot mix asphalt has been<br />
Page 4 of 9
supplied. This fairly reflects the increasing value of the Contractor’s RAP pile when AC<br />
prices are increasing and the opposite when they are declining.<br />
Notes:<br />
1. Contractors should bid the hot mix asphalt item using the MTO PGAC pricing<br />
available at the time of quotation closing. The AC Price Index is only a tool <strong>for</strong><br />
qualifying hot mix prices and is not intended as a standard AC price to be<br />
incorporated into the contract bid.<br />
2. The payment adjustment calculated using this <strong>for</strong>mula is full compensation <strong>for</strong><br />
any and all PGAC grades specified. If the AC index has not changed more than<br />
$15.00 per tonne up or down, no adjustment is required. Only the amount of the<br />
change that is greater than $15.00 is used to calculate payment adjustments.<br />
3. Beginning with the AC Index <strong>for</strong> July 2006 MTO will amend their past practice of<br />
establishing the monthly index amount on the 1stday of the month from the<br />
average of the four weekly AC prices received in the previous month to a<br />
calculation that takes in the average of the four weeks of the current month and<br />
is subsequently published on the last day of that month.<br />
4. As the result of the implementation of Note #4 and the subsequent issue of MTO<br />
SP 103S20 the AC Price index <strong>for</strong> the month prior to quotation opening will be<br />
used as the AC bid price to calculate AC adjustments.<br />
Page 5 of 9
MUNICIPALITY OF NORTH PERTH<br />
BID FORM<br />
FORMAL QUOTATION: <strong>2013</strong> URBAN ASPHALT SUPPLY AND PLACE<br />
Item Quantity Unit Price Total<br />
1. Rocher Road<br />
8 metric tonnes HL4 $ $<br />
2. 430 Inkerman St E<br />
8 metric tonnes HL4 $ $<br />
3. 475 Albert Ave N<br />
6 metric tonnes HL4 $ $<br />
4. Wallace Ave N<br />
104m 2 Coldplane $ $<br />
12 metric tonnes HL4 $ $<br />
5. Main St Intersection<br />
34m 2 Fine grade and proof roll $ $<br />
12 metric tonnes HL4 $ $<br />
Subtotal<br />
13% HST<br />
TOTAL $<br />
Dated at this day of , <strong>2013</strong><br />
NAME OF COMPANY:<br />
SIGNATURE:<br />
ADDRESS:<br />
TELEPHONE:<br />
FAX:<br />
Note: Lowest or any quotation not necessarily accepted.<br />
This quotation is subject to approval by the<br />
Council of North Perth<br />
Page 6 of 9
BEFORE SUBMITTING PLEASE REVIEW THE ATTACHED PAGE<br />
CALLED CHECKLIST FOR FORMAL QUOTATION: <strong>2013</strong> URBAN<br />
ASPHALT SUPPLY AND PLACE QUOTATION REQUIREMENTS<br />
.<br />
Basis of Rejection of <strong>Quotation</strong><br />
<strong>Quotation</strong>s may be rejected <strong>for</strong> any one of the following reasons:<br />
(a)<br />
(b)<br />
(c)<br />
(d)<br />
(e)<br />
(f)<br />
Bids received after closing date.<br />
Bids received on other than the quotation <strong>for</strong>ms supplied.<br />
Bids not completed in ink or by typewriter.<br />
Incomplete bids (all items not bid).<br />
Qualified or conditional bids.<br />
Bids not properly signed and sealed.<br />
CERTIFICATE OF INSURANCE REQUEST<br />
The Municipality of North Perth will require a Certificate of Liability Insurance from you<br />
with this quotation. It must be issued by your insurer or on a standard CSIO <strong>for</strong>m and<br />
signed by an Authorized Representative.<br />
In this certificate, the Municipality will require the following:<br />
1. Your full name and address with contact name & phone number<br />
2. Description of your Business Operation<br />
3. Commercial General Liability with a limit no less than $2,000,000.00<br />
4. Tenants Legal Liability, Cross Liability, Notice of Cancellation (30 Days)<br />
5. The Municipality is to be added and shown as an Additional Insured under<br />
Liability.<br />
6. If a licensed motorized vehicle is being used, we require Confirmation of<br />
Automobile Liability Insurance or Commercial Automobile Liability with a limit no<br />
less than $2,000,000.00.<br />
Workplace Safety Insurance Board Coverage<br />
The Municipality of North Perth will require a current WSIB Clearance Certificate with<br />
this quotation.<br />
Accessibility <strong>for</strong> Ontarians with Disabilities Requirements:<br />
Prior to the commencement of any work under this contract, the successful bidder will<br />
also be required to provide Accessible Customer Service Training to all staff working on<br />
behalf of the Municipality of North Perth in compliance with the requirements of the<br />
Accessibility <strong>for</strong> Customer Service Regulation 429/07, Section 6. The Municipality of<br />
North Perth will offer assistance with appropriate training resources if required.<br />
Page 7 of 9
Health and Safety:<br />
The Municipality will expect the successful bidder to abide by all provincial regulations<br />
regarding health and safety, as well as licensing and certification.<br />
The Municipality of North Perth has a Contractor Health and Safety Package that will<br />
need to be completed by the successful bidder, prior to the start of work, which includes<br />
the submission of the contractors Health and Safety Policy or the agreement to abide by<br />
the Municipality of North Perth’s policies.<br />
GENERAL CONDITIONS<br />
Regulations<br />
The Contractor shall abide by all Acts, By-laws and Regulations relative to the<br />
per<strong>for</strong>mance of the work.<br />
Completion<br />
October 18, <strong>2013</strong>.<br />
Work Limitations<br />
Please note that no work will be permitted at any time where the 24 hour weather<br />
<strong>for</strong>ecast by Environment Canada predicts temperatures of less than 4 degrees Celsius.<br />
Warranty<br />
The contractor shall warranty the work <strong>for</strong> 24 months. All repairs due to deficiencies in<br />
product or workmanship shall be at no cost to the Municipality of North Perth.<br />
Page 8 of 9
Municipality of North Perth<br />
Checklist <strong>for</strong>:<br />
FORMAL QUOTATION: <strong>2013</strong> URBAN ASPHALT SUPPLY AND PLACE<br />
When submitting the quotation, the following documents must be submitted:<br />
Certificate of Insurance<br />
Current WSIB clearance certificate<br />
Bid Form<br />
If you are the successful bidder, the following documents must be submitted prior to the<br />
commencement of work:<br />
Accessibility <strong>for</strong> Ontarians with Disabilities Requirements<br />
Health and Safety Contractor Package: The successful bidder must abide by all<br />
provincial regulations regarding health and safety as well as licensing and<br />
certification. The Contractor Health and Safety Package will need to be<br />
completed prior to the start of work<br />
Page 9 of 9