<strong>Haas</strong> Technical Publications<br />

Lifting Instructions<br />

EC-300/MDC-500 Lifting Hardware Details<br />

1. Before <strong>lifting</strong> the machine, remove the hole<br />

plugs <strong>and</strong> install four 1"-8 TPI forged steel<br />

shoulder eyebolts, 1" steel washers <strong>and</strong><br />

spacers.<br />

EC-300 Only<br />

Top Panels<br />

EC-300 only - Remove the two top panels.<br />

C<br />

42” (107 cm)<br />

16” (41 cm)<br />

2. Once the machine is in position, remove the<br />

eyebolts from the <strong>lifting</strong> holes <strong>and</strong> replace with<br />

bolts <strong>and</strong> washers<br />

3. After installation, re-install the chip screen with<br />

bolts <strong>and</strong> washers.<br />

This dimension is<br />

critical to prevent the<br />

lift chain from<br />

contacting the<br />

spindle head cover.<br />

*<br />

*<br />

25”<br />

(64 cm)<br />

MDC<br />

Chip Screen<br />

DUAL PA LET<br />

INLINE<br />

SPINDLE<br />

*<br />

*<br />

4X Lifting Eyebolt<br />

Spacer<br />

4X Forged Steel Shoulder Eyebolt<br />

1”- 8 TPI <strong>and</strong> 1” Steel Washer<br />

Min 9000 lb Working Load<br />

Limit (WLL) at Vertical Pull (08)<br />

ES0246 Rev AN Jan 2013 Page 14 of 31