Off-loading the <strong>FP</strong> <strong>McCann</strong> <strong>Easi</strong>-<strong>Pit</strong><br />
Spreader Bar<br />
Clamp Grab<br />
3. Off-loading should take the place at the nearest hard road to the point of installation.<br />
The <strong>Easi</strong>-<strong>Pit</strong> must be stored vertically on firm flat ground with the concrete base at the<br />
bottom.<br />
4. Carefully inspect units during off-loading to verify that products are undamaged and<br />
comply with order placed. Two types of check are required:<br />
Visual: Inspect the <strong>Easi</strong>-<strong>Pit</strong> for any sign of damage, including cracked or chipped<br />
concrete, or damage to the inlet / outlet anything that could affect the performance.<br />
Design: Check that the item received is the one ordered. Please note; <strong>Easi</strong>-<strong>Pit</strong>s are<br />
generally ordered in accordance with the Predl Clock system or as specified by the<br />
contractor or engineer. Positions are generally specified in degrees either from 0°to<br />
270°. (A copy of PREDL Clock is included in Appendi x A).<br />
<strong>Easi</strong>-<strong>Pit</strong>s are generally a bespoke product and are labeled with site references, to<br />
include:<br />
• Client / Site Name,<br />
• Site reference (e.g. MH 5),<br />
• Outlet Position<br />
• Production date<br />
F P <strong>McCann</strong> <strong>Ltd</strong> <strong>Easi</strong>-<strong>Pit</strong> <strong>Installation</strong> <strong>Procedure</strong> Version 1.0<br />