(b)<br />
(c)<br />
The price adjustment shall be determined during each quarter from the formula given in the<br />
contract data.<br />
Following expressions and meanings are assigned to the work done during each quarter:<br />
R =<br />
Total value of work done during the quarter. It would include the amount of secured<br />
advance for materials paid for (if any) during the quarter, less the amount of the secured<br />
advance recovered, during the quarter. It will exclude value for works executed under<br />
variations for which price adjustment will be worked separately based on the terms<br />
mutually agreed.<br />
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not covered by the<br />
provisions of this or other clauses in the contract, the unit rates and prices included in the contract shall<br />
be deemed to include amounts to cover the contingency of such other rise or fall in costs.<br />
48. Retention<br />
48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract<br />
Data until Completion of the whole of the Works.<br />
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and<br />
half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified<br />
by the Engineer to the Contractor before the end of this period have been corrected.<br />
48.3 On completion of the whole works, the contractor may substitute retention money(balance half) with an<br />
“on demand” Bank guarantee.<br />
49. Liquidated Damages<br />
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Contract<br />
Data for each day that the Completion Date is later than the Intended Completion Date (for the whole of<br />
the works or the milestone as stated in the contract data). The total amount of liquidated damages shall<br />
not exceed the amount defined in the Contract Data. The Employer may deduct liquidated damages from<br />
payments due to the Contractor. Payment of liquidated damages does not affect the Contractor's<br />
liabilities.<br />
49.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer shall<br />
correct any overpayment of liquidated damages by the Contractor by adjusting the next payment<br />
certificate. The Contractor shall be paid interest on the over payment calculated from the date of<br />
payment to the date of repayment at the rates specified in Sub Clause 43.1.<br />
50. Deleted<br />
51. Advance Payment<br />
51.1 The Employer shall make advance payment to the Contractor of the amounts stated in the Contract Data<br />
by the date stated in the Contract Data, against provision by the Contractor of an Unconditional Bank<br />
Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to the<br />
advance payment. The guarantee shall remain effective until the advance payment has been repaid, but<br />
the amount of the guarantee shall be progressively reduced by the amounts repaid by the Contractor.<br />
Interest will not be charged on the advance payment.<br />
51.2 The Contractor is to use the advance payment only to pay for Equipment, Plant and Mobilization<br />
expenses required specifically for execution of the Works. The Contractor shall demonstrate that<br />