31.05.2015 Views

Download PDF - Hot-Mix Magazine

Download PDF - Hot-Mix Magazine

Download PDF - Hot-Mix Magazine

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

To see the equipment in action, go to<br />

KPI-JCI’s Official Channel on YouTube<br />

to watch “One Tough Customer.”<br />

This project was Moyna’s first Interstate highway recycling job and KPI-JCI’s first setup with an FT5260 and FT6203 crushing and screening as the plants walked the grade.<br />

horizontal shaft impact (HSI)<br />

crushing plant and a KPI-JCI<br />

FT6203 6-ft x 20-ft (1.8 m x 6 m)<br />

three-deck horizontal screen plant,<br />

were delivered to the I-35 site near<br />

Osceola, Iowa, in April 2010.<br />

Moyna’s responsibility for the I-35<br />

project included pulling up the<br />

concrete with its asphalt overlay<br />

in a 10-mile (16 km) stretch<br />

along the northbound lanes. The<br />

milled asphalt was stockpiled<br />

along the outside shoulder.<br />

Moyna broke the concrete with an<br />

excavator and left it piled along<br />

the median shoulder. The asphalttreated<br />

base under the concrete<br />

was then chunked and laid on top<br />

of the asphalt overlay millings.<br />

As the company graded the road<br />

site, it crushed the asphalt with<br />

a KPI-JCI FT4240 closed-circuit<br />

HSI plant and put that material<br />

down on the graded road site<br />

as subbase. The FT5260 and<br />

FT6203 plants then processed<br />

the concrete material, fed at 6-in.<br />

minus, crushing and screening<br />

it to 1-1/2-in. for use as granular<br />

subbase. Marmann explained that<br />

the granular subbase provides<br />

excellent drainage for stormwater<br />

control. And after that step, the<br />

paving contractor for the job<br />

came in behind Moyna, adding<br />

asphalt-treated base followed<br />

by concrete pavement slabs to<br />

complete the project. Moyna’s<br />

role in the project wrapped up in<br />

August.<br />

Set Up and Go<br />

According to Marmann, when<br />

RMS delivered the plants, the<br />

dealer provided a pre-delivery<br />

inspection followed by setup and<br />

training. After that, Moyna put the<br />

plants to work and hasn’t looked<br />

back since.<br />

This project was Moyna’s first<br />

Interstate highway recycling job,<br />

and it was KPI-JCI’s first setup<br />

with an FT5260 and FT6203<br />

crushing and screening as the<br />

plants walked the grade. “For a<br />

first time for both sides, it went<br />

really well,” said Marmann. “If<br />

we had questions or little tweaks<br />

that needed to be done for our<br />

applications, between RMS and<br />

KPI-JCI, we could talk to them<br />

one day and have a solution by<br />

the next. It was pretty flawless.<br />

And the beauty of it—this setup<br />

is so versatile and useable—at<br />

one point when we needed<br />

material really quickly in one of<br />

our pits, we pulled the plants off<br />

of the I-35 job, unloaded at the<br />

pit, put the plants together and<br />

started crushing, just like that.”<br />

From the start, the tracked<br />

crusher and screen proved their<br />

worth under tight deadlines and<br />

unpredictable conditions. “We’ve<br />

had incredible amounts of rain<br />

in Iowa in the last two to three<br />

years,” Marmann said. “We have<br />

to have machines that work well<br />

when the sun shines, and also<br />

allow us to do some recycle<br />

processing in the rain. We used<br />

the equipment on the I-35 job for<br />

several weeks; then pulled it for<br />

about three weeks to use it at the<br />

Cedar Rapids airport, crushing<br />

old runway material for reuse;<br />

then we took it back to I-35.”<br />

In spite of heavy rain throughout<br />

southeast Iowa (from May 1 to<br />

mid-July 2010, the region had<br />

seen more than 55 inches of<br />

rain) and pulling the new KPI-<br />

JCI plants for other applications,<br />

CJ Moyna ultimately was able<br />

to complete its I-35 project on<br />

time and within budget. And<br />

the factors that helped Moyna<br />

meet its goals? “We had good<br />

equipment, and some fortunate<br />

weather breaks. The material<br />

itself also provided some<br />

breaks—we had good luck with<br />

our material,” Marmann said.<br />

“And personnel stepped up to<br />

meet the challenge. But if the<br />

equipment hadn’t performed<br />

for us, it would have been hard<br />

for us to make up for that lost<br />

time.” <br />

FOR MORE INFORMATION<br />

about KPI-JCI equipment, contact Ron Griess:<br />

800-542-9311<br />

Fax: 605-665-8858 • E-mail: rongriess@kolbergpioneer.com<br />

HOT-MIX MAGAZINE 28 VOLUME 16 NUMBER 1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!